Appellate Division: Second Judicial Department
M79747
S/sl
|
2008-05724
James Erwin, respondent, v Farrell Building Company, Inc., et al., appellants-respondents, McLoughlin Construction Corp., respondent-appellant. (Index No. 20413-06)
| ORDER ON APPLICATION |
Joint application by the appellants-respondents and the respondent-appellant pursuant to 22 NYCRR 670.8(d)(2) to enlarge the time to perfect an appeal and cross appeal from an order of the Supreme Court, Suffolk County, dated May 20, 2008.
ORDERED that the application is granted; and it is further,
ORDERED that the appellants-respondents' time to perfect the appeal is enlarged until February 24, 2009, and the joint record or appendix on appeal (see 22 NYCRR 670.8[c][1]) and the appellants-respondents' brief must be served and filed on or before that date; and it is further,
ORDERED that the respondent-appellant shall serve and file its answering brief, including its points of argument on the cross appeal, in accordance with the rules of this court (see 22 NYCRR 670.8[c][3]).
ENTER:
James Edward Pelzer
Clerk of the Court