D. Owens Electric, Inc. v J.W.Mays, Inc.
Motion No: 2016-11355
Slip Opinion No: 2017 NY Slip Op 80217(U)
Decided on July 18, 2017
Appellate Division, Second Department, Motion Decision
Published by New York State Law Reporting Bureau pursuant to Judiciary Law § 431.
This motion is uncorrected and is not subject to publication in the Official Reports.


Supreme Court of the State of New York

Appellate Division: Second Judicial Department

M234728

X/ct

2016-11355

D. Owens Electric, Inc., plaintiff-respondent,

v J.W. Mays, Inc., appellant, P.J. Exteriors, Inc.,

et al., defendants, Jason Coschignano, doing

business as JC Construction, defendant-respondent.

(Action No. 1)

Mid-Hudson Structural Concrete, Inc.,

doing business as Recycle Depot, plaintiff-responden

v J.W. Mays, Inc., appellant, P.J. Exteriors, Inc.,

et al., defendants, Jason Coschignano, doing

business as JC Construction, defendant-respondent.

(Action No. 2)

BSB Construction, Inc., plaintiff-respondent,

v J.W. Mays, Inc., appellant, P.J. Exteriors, Inc.,

et al., defendants, Jason Coschignano, doing business

as JC Construction, defendant-respondent.

(Action No. 3)

(Index Nos. 80001/14, 50519/14, 50518/14)

ORDER ON APPLICATION







t,

Application by the appellant pursuant to 22 NYCRR 670.8(d)(2) to enlarge the time to perfect an appeal from an order of the Supreme Court, Dutchess County, dated September 29, 2016.

Upon the papers filed in support of the application and no papers filed in opposition or in relation thereto, it is

ORDERED that the application is granted, the appellant's time to perfect the appeal is enlarged until July 27, 2017, and the record or appendix on the appeal and the appellant's brief shall be served and filed on or before that date.

ENTER:

Aprilanne Agostino

Clerk of the Court