| Maidman Family Parking, LP v Wallace Indus., Inc. |
| 2016 NY Slip Op 08148 [145 AD3d 1165] |
| December 1, 2016 |
| Appellate Division, Third Department |
| Published by New York State Law Reporting Bureau pursuant to Judiciary Law § 431. |
| Maidman Family Parking, LP, Respondent, v Wallace Industries, Inc., et al., Appellants. |
Neil T. Wallace, Williamsburg, Virginia and Coughlin & Gerhart, LLP, Binghamton (Oliver N. Blaise III of counsel), for appellants.
Levene Gouldin & Thompson, LLP, Vestal (Scott R. Kurkoski of counsel), for respondent.
Devine, J. Appeal from an order of the Supreme Court (Rumsey, J.), entered September 18, 2015 in Tompkins County, which, among other things, denied defendants' motion to dismiss the complaint.
Defendants Combustion Products Management, Inc., CPM Virginia, LLC, CPM Pennsylvania LLC and CPM Golf, LLC borrowed $155,186.46 from plaintiff and, in 2004, defendant Neil Wallace signed a promissory note for that amount in his capacity as president or sole member of those entities. Defendant Wallace Industries, Inc. simultaneously borrowed $244,813.54 from plaintiff, and Wallace, its corporate president, executed a promissory note to that effect. The notes were secured by separate mortgages on real property owned by Wallace Industries in the City of Ithaca, Tompkins County. Wallace personally guaranteed both notes and additionally gave a guarantee on behalf of Wallace Industries.
The notes were due and payable on June 30, 2005, and it is undisputed that no payments were made. Despite the default, plaintiff did not commence this action to recover the debt owed and to foreclose upon the mortgages until July 2, 2015, well beyond the six-year limitations period (see CPLR 213). Defendants filed a pre-answer motion to dismiss the complaint alleging, among other things, that it was time-barred. Supreme Court denied the motion in relevant part, agreeing with plaintiff that the action was timely inasmuch as defendants recognized the debts so [*2]as to take the "action out of the operation of the provisions of limitations of time for commencing actions" (General Obligations Law § 17-101). Defendants appeal, and we now affirm.
"In order to meet the requirements of [General Obligations Law § 17-101], a writing must be signed, recognize an existing debt and contain nothing inconsistent with an intention on the debtor's part to pay it" (Sitkiewicz v County of Sullivan, 256 AD2d 884, 886 [1998], appeal dismissed and lv dismissed 93 NY2d 908 [1999]; see Hon Fui Hui v East Broadway Mall, Inc., 4 NY3d 790, 791 [2005]; Lew Morris Demolition Co. v Board of Educ. of City of N.Y., 40 NY2d 516, 521 [1976]). Here, Wallace signed an August 26, 2010 letter in which he acknowledged the principal amount and maturity date for each loan and, indeed, agreed to waive any statute of limitations defense available to defendants against "any claim [by plaintiff] to enforce collection of any monies due [it] arising out of the" loans. This language "clearly conveys and is consistent with an intention to pay, which is all that need be shown in order to satisfy" the statute, even if the phrasing implies that the sums owed by defendants might vary from the original principal amounts (Banco do Brasil v State of Antigua & Barbuda, 268 AD2d 75, 77 [2000]; see Chase Manhattan Bank v Polimeni, 258 AD2d 361, 361 [1999], lv dismissed 93 NY2d 952 [1999]).[FN*] A renewed statute of limitations for plaintiff's claims accordingly began to run no earlier than August 26, 2010 and, thus, the commencement of this action on July 2, 2015 was timely.
Defendants' remaining contentions, to the extent that they are not academic in light of the foregoing, have been examined and rejected.
Garry, J.P., Egan Jr. and Rose, JJ., concur. Ordered that the order is affirmed, with costs.