Inter Metal Fabricator Inc. v HRH Constr. LLC
2007 NY Slip Op 05317 [41 AD3d 210]
Decided on June 14, 2007
Appellate Division, First Department
Published by New York State Law Reporting Bureau pursuant to Judiciary Law § 431.
This opinion is uncorrected and subject to revision before publication in the Official Reports.


Decided on June 14, 2007
Andrias, J.P., Saxe, Friedman, Nardelli, Malone, JJ.

1329
Index 604137/04

[*1]Inter Metal Fabricator Inc., Plaintiff-Appellant,

v

HRH Construction LLC, et al., Defendants-Respondents.





Goldberg & Connolly, Rockville Centre (Brian P. Craig of
counsel), for appellant.
Wasserman Grubin & Rogers, LLP, New York (Samuel A.
Gunsburg of counsel), for respondents.

Order, Supreme Court, New York County (Karla Moskowitz, J.), entered January 13, 2006, which, to the extent appealed from, granted defendants' motion to dismiss the fifth cause of action in the Fourth Amended Complaint, seeking delay damages, unanimously affirmed, without costs.

We affirm the dismissal of the claim for delay damages upon the ground that it is premature. The contract bars claims against the construction manager "on account of the Contract Price for the Project" until the completion of available mechanic's lien enforcement actions, and two such causes of action are alleged in the Fourth Amended Complaint. Although plaintiff contends that the clause requiring exhaustion of Lien Law remedies is unenforceable, the provision at issue does not offend the prohibition against indefinitely suspending a
contractor's right to enforce its mechanics' liens (cf. West-Fair Elec. Contrs. v Aetna Cas. & Sur. Co., 87 NY2d 148 [1995]). Moreover, even if the claim for delay damages was not premature, it would be barred by the "no-damages-for-delay" provision contained in the parties' contract.

THIS CONSTITUTES THE DECISION AND ORDER
OF THE SUPREME COURT, APPELLATE DIVISION, FIRST DEPARTMENT.

ENTERED: JUNE 14, 2007

CLERK