| SMC Elec. Contrs., Corp. v TSSCO, Inc. |
| 2009 NY Slip Op 51845(U) [24 Misc 3d 1242(A)] |
| Decided on August 10, 2009 |
| Supreme Court, New York County |
| Madden, J. |
| Published by New York State Law Reporting Bureau pursuant to Judiciary Law § 431. |
| This opinion is uncorrected and will not be published in the printed Official Reports. |
SMC Electrical
Contractors, Corp., Petitioner
against TSSCO, Inc., Respondent. |
Petitioner SMC Electrical Contractors, Corp., ("SMC") moves, by order to
show cause, for (i) an order pursuant to New York Lien Law § 21-a discharging a lien filed
by respondent TSSCO, Inc., ("TSSCO") against a New York Harbor High School construction
project ("Harbor High Project"), which the New York City School Construction Authority
("SCA") operates, and (ii) an order pursuant to New York Lien Law § 39 and 39-A voiding
the lien and granting it statutory damages and costs against TSSCO for willfully exaggerating the
lien.
SMC is an electrical subcontractor for the general contractor M. A. Angeliades on the Harbor High Project. (Kazantzis Affid. ¶ 5). For this project, SMC retained the electrical supplier TSSCO via a purchase order on on June 26, 2006, for "fire, intrusion, intercom, phone, clock, & sound systems." (Kazantzis Affid. Ex. A). Prior to the delivery and installation of any material for the project, the SCA required TSSCO to provide work proposals and shop drawings for approval by the SCA project engineer, DVL Engineering ("DVL"). (Kazantzis Affid. ¶ 16). TSSCO employees A. Abruzzo and Eric Gursky drafted technical diagrams for these systems, (Kazantzis Affid. Ex. 1), diagrams which employee Fran Garcia submitted (Kazantzis Affid. ¶ 14). As both SMC and TSSCO agree, these employees do not hold licenses as architects, engineers, or surveyors, (see id., Affirm. in Opp. ¶ 10), and the diagrams do not bear the seal of any such licensed professional (see Kazantzis Affid. Ex. 1).
On July 25, 2008, and August 8, 2008, DVL rejected all but one of TSSCO's submissions and directed TSSCO to "resubmit as specified." (Kazantzis Affid. Ex. B).
The parties' accounts, although not irreconcilable, differ as to what occurred afterward. SMC alleges that "TSSCO never submitted acceptable work proposals [or] shop drawings to DVL so as to be able to contractually deliver the materials to the Harbor High Project, and never performed the one item of work that was approved." (Kazantzis Affid. ¶ 21). TSSCO claims that it "proceeded to make the revisions and submit [sic] them to SMC," (Bradley Affid. ¶ 8), and that it "further proceeded to commence ordering the project materials, create sales orders, and procurement documents," (Bradley Affid. ¶ 9), but that "[a]fter [TSSCO] performed this work, SMC ceased communicating with [TSSCO]. . . . In December, 2008, SMC asked that we only perform a portion of the work at a new price," (Bradley Affid. ¶ 10). [*2]
On January 14, 2008, TSSCO filed a lien on the Harbor High Project for $36,500, and, in the lien Notice, indicated that "the labor performed and material furnished were[:] Supplied and Installed Low Voltage Equipment, Engineering, Program[m]ing, Testing, Training, Etc." (Bradley Affid. Ex. D). On January 26, 2009, SMC served a Demand for a Verified Statement of the lien pursuant to New York Lien Law § 38. (Kazantzis Affid. Ex. D). On February 9, 2009, TSSCO provided an itemized statement to SMC which states that "[t]he total amount of labor attributable to the original contract before termination is $36,857.50 consisting of sales, engineering, drafting, supervision and clerical. The total amount of materials attributable to the original contract is $350.00 consisting of postage and freight. The total amount due and owing is $37,307.50 which is comprised of the following. See breakdown appended hereto." (Id.). However, the attached documents, which include the purchase order, do not appear to break down the expenses any more extensively. (Id.).
On January 29, 2009, SMC alleges it served a demand for foreclosure on TSSCO pursuant to New York Lien Law § 21-a. (Kazantzis Affid. ¶ 35; Kazantzis Affid. Ex. E). The Affidavit of Service indicates that the process server hand-delivered the demand on an employee named Melinda who refused to provide her full name. (Kazantzis Affid. Ex. E). TSSCO denies receiving service and claims that its employees "do not refuse to give names if legal papers are served." (Bradley Affid. ¶ 13). In any case, TSSCO did not thereafter commence foreclosure proceedings or serve SMC with a notice of pendency. (Kazantzis Affid. ¶ 37).
SMC argues that because TSSCO failed to commence foreclosure proceedings or file a notice of pendency within thirty days since SMC served the demand for foreclosure, the court should vacate the lien. SMC further asserts that since TSSCO did not have a licensed architect, engineer, or surveyor draft its submitted drawings, and since the owner's agent, DVL, rejected its submissions, such drawings were not lienable improvements. As an extension of this argument, SMC claims that TSSCO exaggerated the lien amount, as its items were not lienable, and as the verified itemization was an insufficient response to the requirements of New York Lien Law § 38.
TSSCO counters that courts can only summarily discharge a lien under Lien Law § 21(7), and that preliminary plans are lienable even if no actual work occurred on the property. TSSCO denies the need to have a licensed professional stamp its technical drawings since SMC's licensed electrician would later incorporate the drawings into SMC's filings with the SCA. TSSCO also argues that the law reserves willful exaggeration claims for trial. Finally, TSSCO requests a traverse hearing to resolve whether SMC properly served the demand for foreclosure.
In reply, SMC argues that whether TSSCO's drawings were lienable by TSSCO against
SMC depends solely on whether TSSCO's draftsmen possessed licenses as architects, engineers,
or surveyors. SMC avers that since the parties do not dispute the facts surrounding TSSCO's
drawings, the court can make a willfulness determination on the record. Finally, SMC concludes
that TSSCO's denial that it received service for the demand for foreclosure was a self-serving,
conclusory affidavit not entitled to factual credence.
Accordingly, it is hereby
ORDERED that TSSCO's request for a traverse hearing is granted, and it is further
ORDERED that the issue of whether TSSCO was properly served with the demand is referred to a Special Referee to hear and report with recommendations, except that in the event of and upon the filing of a stipulation as permitted by CPLR 4317, the Special Referee or other person designated as referee shall determine said issue; and it is further
ORDERED that aspect of the application to discharge the lien pursuant to Lien Law § [*5]21-a is held in abeyance pending receipt of the report and recommendations of the Special Referee and a motion pursuant to CPLR 4403 or receipt of the determination of the Special Referee or the designated Referee; and it is further
ORDERED that a copy of this order with notice of entry shall be served on the Clerk of the Judicial Support Office (Room 311) on or before September 4, 2009 to arrange a date for reference to a Special Referee; and it is further
ORDERED that failure to timely comply with the immediately preceding paragraph shall result in the denial and dismissal of the remainder of the application; and it is further
ORDERED that the application is denied and dismissed to the extent that it seeks to discharge the lien based on Lien Law § 21(7), and to void the lien for willful exaggeration under Lien Law § 39, and to obtain damages under Lien Law § 39-a.
Dated: August ___, 2009______________________________
J.S.C.