| TR Constr. v Fischer |
| 2010 NY Slip Op 50462(U) [26 Misc 3d 1238(A)] |
| Decided on February 9, 2010 |
| Watertown City Ct |
| Harberson, J. |
| Published by New York State Law Reporting Bureau pursuant to Judiciary Law § 431. |
| This opinion is uncorrected and will not be published in the printed Official Reports. |
TR Construction,
Plaintiff,
against Shameice Fischer, Defendant. |
Issue
May City Court entertain small claims construction litigation if no valid contract existed and
court lacks equity jurisdiction?
This case arises from a construction contract claim. Plaintiff TR Construction (Robert Stephenson, Contractor) sued Defendant Shameice Fischer over a September 29, 2009, contract [*2]for $5,500 of construction work upon Defendant's Watertown residence, seeking $4,000 for work already performed.
Each party submitted paperwork purportedly representing the contract between them.
Plaintiff provided an undated invoice entitled "Final Bill" and apparently signed by Mr.
Stephenson, listing a variety of services either to be provided or which had been provided and
indicating a total due of $4,000 ($5,500 less a $1,500 down payment). Defendant provided
another document signed and dated by both parties detailing work to be performed on her house,
completion timelines and payment details. It specifies that Defendant provided a $1,500 down
payment with $2,500 owed upon completion ("less 5% of the original price quote, $200, to be
paid upon completion of all work").
Two points of law govern disposition of this case. The first, General Business Law §
771 invalidates home improvement contracts not substantially satisfying its requirements.
See Frank v. Feiss, 266 AD2d 825, 826 (4th Dept. 1999);. See also GBL §
771. The second, Uniform City Court Act § 1801, denies small claims courts equity
jurisdiction, even over contract disputes where the court determines the contract is
unenforceable. UCCA § 1801; David. D. Siegel, Plaintiff's failure to comply with GBL §
771 in drafting the agreement he hoped would govern this matter prevented it from becoming an
enforceable contract. See Frank v. Feiss, supra, at 826 ("[T]he failure of plaintiff
to enter into a signed written home improvement contract in conformity with General Business
Law § 771 bars recovery based upon breach of contract."); Harter v. Krause, 250
AD2d 984, 986 (3d Dept. 1998) ("[F]ailure to strictly comply with the statute [§ 771] bars
recovery under an oral or insufficiently detailed written home improvement contract . . .");
Mindich Developers, Inc. v. Milstein, 227 AD2d 536, 537 (2d Dept. 1996) ("We find . . .
that the plaintiff cannot recover for lost profits for work not performed where there was . . . [no]
strict compliance with [GBL 771] . . . ."). The contract here lacks several provisions, including
§ 771(1)(d)'s required warning that an unpaid contractor may have a mechanic's lien against
the owner's property. GBL § 771(1)(d). Also missing are subsection (1)(e)'s notice that
contractors must deposit pre-completion payments in accordance with New York's lien law or
take other steps to protect the money prior to completion and subsection [*3](1)(h)'s provision permitting an owner three days to cancel the
contract unless the work occurs on an emergency basis. GBL §§ 771(1)(e),
(h).[FN1]
The Court is aware of other cases in the Second Department upholding construction
agreements notwithstanding § 771 omissions. See Island Wide Heating & Air
Conditioning v. Sachs, 189 Misc 2d 355, 356 (2d Dept. 2001); Porter v. Bryant, 256
AD2d 395 (2d Dept. 1998); Wowaka & Sons, Inc. v. Pardell, 242 AD2d 1, 3-5 (2d Dept.
1998); see also 21 Besides being obliged to adhere to the Fourth Department's holding in Frank v.
Feiss, this Court can surmise at least one "cogent argument" supporting perfect compliance
as a requirement of § 771 contracts. It is that Pardell, Bryant and
Sachs put a judicial gloss upon the statute permitting compliance with the spirit of the
law (as opposed to its letter) of the sort that the Fourth Department has specifically condemned.
See Cucinotta v. Hanulak, 231 AD2d 904, 905 (4th Dept. 1996). In Hanulak, the
Fourth Department overruled a lower court's sua sponte amendment of Real Property Law §
227-a(2) to render timely a senior citizen's untimely notice of vacation to her landlord: "[T]he
order and judgment cannot be sustained on grounds of equity and fair play or on the ground that
plaintiff complied with the statute in spirit.'" Id. Doing so, the court observed,
effectively conferred equity powers upon a court specifically forbidden them. [*4]See Id. (citing Siegel, The parties' failure to create an enforceable contract normally would not preclude relief
under quantum meruit (see Frank v. Feiss, at 364; Harter v. Krause at 547).
However, as noted above, this Court lacks the equity jurisdiction necessary to provide it. UCCA
§ 1801; Hanulak at 905; Siegel, supra, The Case is dismissed.
This Opinion shall serve as the Judgment and Order of the Court:
III.
IV.
Entered: February 9, 2010____________________________________
Date: February 9, 2010Hon. Judge James C. Harberson, Jr.
Footnote 1: Subsection (h) provides in
relevant part: "A notice to the owner that, in addition to any right otherwise to revoke an offer,
the owner may cancel the home improvement contract until midnight of the third business day
after the day on which the owner has signed an agreement or offer to purchase relating to such
contract. Cancellation occurs when written notice of cancellation is given to the home
improvement contractor. Notice of cancellation, if given by mail, shall be deemed given when
deposited in a mailbox properly addressed and postage prepaid. Notice of cancellation shall be
sufficient if it indicates the intention of the owner not to be bound." GBL § 771(1)(h)