| Mavroidis v Papagiannopoulos |
| 2010 NY Slip Op 51249(U) [28 Misc 3d 130(A)] |
| Decided on July 16, 2010 |
| Appellate Term, Second Department |
| Published by New York State Law Reporting Bureau pursuant to Judiciary Law § 431. |
| This opinion is uncorrected and will not be published in the printed Official Reports. |
Appeal, on the ground of inadequacy, from a judgment of the Civil Court of the City of New
York, Queens County (Timothy J. Dufficy, J.), entered July 9, 2008. The judgment, after a
nonjury trial, awarded plaintiff the principal sum of $300.
ORDERED that the judgment, insofar as appealed from, is affirmed without costs.
Plaintiff commenced this small claims action against defendant, a contractor, based on a claim of defective work. Following a nonjury trial, the Civil Court awarded plaintiff the sum of $300. Plaintiff appeals on the ground of inadequacy.
At trial, it was established that plaintiff had commenced a separate small claims action to
recover for the same defective work against Prime Contracting, the company that she had paid to
perform the work at issue, and that plaintiff had accepted $3,500 from Prime Contracting in
settlement of that action. Defendant testified that he had
never entered into an agreement directly with plaintiff to perform any work, nor did he
have anything to do with the project. Plaintiff, on the other hand, testified that Prime Contracting
had completed all of the work being sued upon with the exception of electrical work which
defendant had performed. While plaintiff further testified that she had hired defendant to do the
work at issue, and that defendant had then "sold" the job to Prime Contracting, she also stated
that during the pendency of the work she understood that Prime Contracting was the only
contractor on the job and that she had paid Prime Contracting, and only Prime Contracting, for
the work at issue, including the electrical work. In view of the foregoing, and taking into account
plaintiff's [*2]commencement and settlement of the prior lawsuit
against Prime Contracting for the work at issue in this lawsuit, this action should have been
dismissed, as plaintiff has failed to establish a prima facie case against the defendant herein.
However, because defendant did not cross-appeal from the judgment awarding plaintiff $300, we
leave the judgment undisturbed and find that it rendered substantial justice between the parties in
accordance with the rules and principles of substantive law (CCA 1807).
Pesce, P.J., Weston and Golia, JJ., concur.
Decision Date: July 16, 2010