| Matter of 29 Flatbush Assoc. LLC v New York State Dept. of Envtl. Conservation |
| 2011 NY Slip Op 50407(U) [30 Misc 3d 1239(A)] |
| Decided on March 22, 2011 |
| Supreme Court, Kings County |
| Schack, J. |
| Published by New York State Law Reporting Bureau pursuant to Judiciary Law § 431. |
| This opinion is uncorrected and will not be published in the printed Official Reports. |
In the Matter of 29
Flatbush Associates, LLC, Petitioner,
against New York State Department of Environmental Conservation, Alexander B. Grannis, as Commissioner of the New York State Department of Environmental Conservation, and Dale A. Desnoyers, as Director of the Division of Environmental Remediation, Respondents. |
The following papers numbered 1 to 3 read on this motion:Papers
Numbered:
Notice of Motion and Affidavits (Affirmations)____________1
Supporting Memorandum of Law_______________________2
Opposing Memorandum of Law________________________3
____________________________________________________________________
____
Petitioner, 29 FLATBUSH AVENUE ASSOCIATES, LLC (FLATBUSH), moves to
reargue, pursuant to CPLR Rule 2221 (d), my May 3, 2010 decision and order in this Article 78
proceeding. This decision was published by the New York State Official Reporter at 27 Misc 3d
1217 (A). The May 3, 2010 decision and order vacated the April 28, 2009 determination by
respondent I held that DEC's April 28, 2009 determination was arbitrary and capricious or an abuse of
discretion and remanded the matter to DEC for further consideration in light of my May 3, 2010
decision and order. I ordered FLATBUSH to perform further investigations at the Site,
specifically: a groundwater investigation, a soil vapor investigation, the completion of a soil
characterization analysis and a magnetometer survey; and, to submit the investigation results to
DEC with documented results of petitioner FLATBUSH's efforts to obtain financing for the
subject project and documentation demonstrating petitioner FLATBUSH's alleged inability to
proceed with the project unless the Site is accepted into the BCP. Further, I ordered DEC,
pursuant to ECL § 27-1407 (6), to use all best efforts to notify petitioner FLATBUSH
within forty-five days after receiving the above information that its BCP application is either
accepted or rejected.
Petitioner FLATBUSH does not reargue those portions of my May 3, 2010 decision and
order holding that DEC's denial of the Site's admission into the BCP was arbitrary and capricious
or an abuse of discretion, but seeks to reargue those limited portions of my May 3, 2010 decision
and order that petitioner FLATBUSH submit to DEC: the results of my ordered further
investigations at the Site; and, the results of petitioner FLATBUSH's efforts to obtain financing
and petitioner FLATBUSH's alleged inability to proceed with the project unless it is accepted
into the BCP. Petitioner FLATBUSH alleges that the following, at *11 of my May 3, 2010
decision and order, is a matter of law misapprehended by the Court - "[a]lthough DEC's denial of
petitioner's application is improper, it does not automatically follow that the petitioner's BCP
application should be granted. The record is incomplete." Petitioner FLATBUSH claims that
there is sufficient information in DEC's Administrative Record (AR) for the Court to have
directed DEC to include the Site into the BCP. Respondents argue that my May 3, 2010 decision
and order did not overlook or misapprehend any material facts or controlling principles of law.
Moreover, petitioner FLATBUSH seeks an award of its costs, disbursements, legal and [*2]other fees, which resulted in my May 3, 2010 decision and order
and this motion to reargue, pursuant to CPLR Article 86, the "New York State Equal Access to
Justice Act."
After hearing oral arguments by counsel for petitioner FLATBUSH and respondents, and
after reviewing all papers, the Court grants petitioner FLATBUSH leave to reargue those
portions of my May 3, 2010 decision and order that it alleges that the Court misapprehended.
Upon reargument, I continue to hold that DEC's April 28, 2009 determination, denying petitioner
FLATBUSH's application for the Site's inclusion in the BCP, pursuant to Environmental
Conservation Law § 27-1401 et seq., is arbitrary and capricious or an abuse of
discretion and uphold vacating DEC's April 28, 2009 determination. Further, I now hold that: the
AR is complete; the Site at 29 Flatbush Avenue is admitted forthwith into the BCP; and
petitioner FLATBUSH is granted an award of its costs, disbursements, legal and other fees,
which resulted in my May 3, 2010 decision and order and this motion to reargue, pursuant to
CPLR Article 86.
Petitioner FLATBUSH is the owner
of the Site, near the intersection of Fulton Street and Flatbush Avenue, which petitioner
purchased for $28,000,000 in November 2007. Petitioner applied to respondent DEC to
participate in the BCP, pursuant to ECL, Article 27, Title 14, because contaminants present at the
site were sufficient to allow its participation and inclusion. Respondent DEC denied petitioner's
application for the Site to be included in the BCP, in a letter, dated April 28, 2009, from
respondent DALE A. DESNOYERS (DESNOYERS), Director of DEC's Division of
Environmental Remediation, to petitioner and petitioner's counsel.
Subsequently, petitioner FLATBUSH commenced the instant Article 78
The New York State Legislature enacted the Brownfield Cleanup Program Act
BCP participation is subject to DEC approval. (ECL § 27-1407 [1]). The BCPA
requires, among other things, that an application be made to DEC, commencing a DEC
investigation and a public notification process. (ECL § 27-1407 [5]). Then, DEC decides
whether to accept or reject the BCP application. DEC, in determining BCP eligibility, considers
only "contamination" from on site sources. (6 NYCRR § 375-3.3 [2]). DEC does not
consider "historic fill material" as a contaminant.DEC is authorized to "[i]ssue and amend
guidance memoranda and similar
Further, DEC has the general power to "[a]dopt such rules, regulations and
DEC developed specific risk levels, with tables of numeric and contaminant specific "soil
cleanup objectives" (SCOs), to protect public health and the environment for three types of land
use - unrestricted (residential use), commercial, and industrial. (ECL § 27-1415 [6]). "[T]he
BCP affords applicants the flexibility to employ the tables or site-specific criteria to determine
acceptable levels of residual contamination, based on four different cleanup tracks.'" [*4](Lighthouse Pointe Prop. Assocs. LLC v New York State Dept. of
Environmental Conservation, 14 NY3d 161, 166 [2010]). In the instant proceeding,
petitioner FLATBUSH elected a track 1 remedial program, which "generally achieves a cleanup
level and the SCOs appropriate for unrestricted residential use (as published in the relevant
generic table) without reliance on any institutional . . . or engineering controls." (Lighthouse
Point at footnote 2, citing ECL § 27-1415 [4]). The Phase I Environmental Site Assessment revealed no evidence of "recognized
environmental conditions," except for: surface-level spills of hydraulic fluid which may contain
PCBs [AR at 38]; and, the possibility that demolition debris or subsurface improvements
remained at the site from former improvements [AR at 39]. The Phase I consultant recommended
that "during site redevelopment activities the soils at the [property] are handled and disposed of
in accordance with all applicable governmental regulations [AR at 38]" and that "[i]n the event
that building debris, tanks, etc. are encountered during the excavation activities, . . . that they are
closed or disposed of in accordance with applicable local regulations [AR at 39]."
The Limited Subsurface Investigation Report found "the presence of semi-volatile organic
compounds [SVOCs] in the north and southwest portions of the Site at concentrations 2 orders of
magnitude greater than their respective regulatory standard [AR at 848]." The Report
recommended that DEC's Spill Hotline be contacted and informed about the elevated levels of
SVOCs and the soil in the northern and southeast portions of the site should be excavated and
removed [AR at 864].
Subsequently, petitioner sent an additional investigation report to DEC, for review in
conjunction with its BCP application [AR at 917-1603], containing a supplemental soil sampling
collected by or for petitioner's consultant, Langan Engineering & Environmental Services, from
non-native fill material and native soil at the site [AR at 920-921]. The supplemental soil testing
report found contamination in non-native fill material, but none in native soil [AR at
922].Respondent DEC denied petitioner's BCP application on April 28, 2009, claiming that the
Site did not meet the statutory definition of a "Brownfield," stating, in relevant part:
Contamination consisting of lead and semi-volatile organic
compounds ("SVOC") is present on the Site. The Application,
the supplemental soil sampling results and other underlying data
[*5] submitted to the Department indicated that there are
concentrations
on the Site of seven (7) SVOC compounds that exceed the Department's
regulatory remediation objectives as stated in 6 NYCRR Part 375.
However, these soil sampling results do not indicate that there will
be any complications of the Site's future development as contamination
[sic]. Further, they appear to be the result of historic fill materials
only.
In addition, the contamination discovered by this data appears
to be minimal when compared to the vast majority of the sampling
(approximately 39 total samples) and the total number of SVOC
contaminants detected (19 in total). Finally, the random locations
and concentrations of the SVOC discovered in Site soils indicates
of the Site
would generate additional costs or complications due to
that issue.A review of the BCP application sampling data also indicates
the presence of one sample with an extremely high lead concentration.
However, this lead sample appears to be isolated due to the lack of
similar sampling results both in proximity of the sample in question
or elsewhere on the Site. In addition, TCLP [Toxicity Characteristic
Leaching Procedure] analysis was done on the lead samples, including
the sample with the highest concentration (11,400 mg/kg). The results
of that sampling indicated that none of the samples exceeded the
hazardous waste threshold (i.e., 5 mg/l) for lead as set forth in
Title 6 of NYCRR Part 371. Also, the supplemental soil sampling
results submitted in July 2008, demonstrated that the identified lead
contamination in soil is isolated both vertically and horizontally.
This makes it unlikely that there is lead contamination on the Site
which would require remediation. Therefore, it is highly unlikely
that there is sufficient lead contamination present to complicate
the redevelopment of the Site.
Additional factors used to make this determination include:
1.The historical uses of the Site since 1900 (theater and parking lot)
make it highly unlikely that sufficient contamination or potential contamination was
generated via these uses and then released to
the Site in concentrations that would complicate the redevelopment
of the Site;
2.The Department finds no conclusive data to indicate that there
still may be unclosed or leaking underground storage tanks on
the Site which could complicate redevelopment;
3.The applicant did not undertake (or provide) groundwater
sampling for the Site which may have revealed additional
[*6] types and sources of contamination that could complicate
redevelopment [; and]4.The Department also notes that the area was recently rezoned
and during the rezoning process the City did not identify any
environmental factors that would qualify the Site for New
York City's E-Designation Environmental Review Program
for Hazardous Materials, Air Quality and Window/Wall
Noise Attenuation (AR at 1615-1616).
Petitioner commenced the instant CPLR Article 78 proceeding to challenge the validity of
DEC's April 28, 2009 determination with respect to the Site and the BCP.
A reviewing court will not substitute its judgment for that of the agency unless the agency's
determination was arbitrary, capricious, or contrary to law (see Pell at 231), and "where .
. . the judgment of the agency involves factual evaluations in the area of the agency's expertise
and is supported by the record, such judgment must be accorded great weight and judicial
deference." (Flacke v Onondaga Landfill Sys., Inc., 69 NY2d 355, 363 [1987]). On the
other hand, "[w]here, however, the question is one of pure statutory reading and analysis,
dependent only on accurate apprehension of legislative intent, there is little basis to rely on
any special competence or expertise of the administrative agency and its interpretive regulations
are therefore accorded much less weight [Emphasis added]." (Kurcsics v
Merchants Mut. Ins. Co., 49 NY2d 451, 459 [1980]). Further, "if the regulation runs counter
to the clear wording of a statutory provision, it should not be accorded any weight."
(Kurcsics at 459). The Court of Appeals, in Lighthouse Pointe at 176, held that
"[t]he meaning of the term brownfield site' presents such a question . . . In Lighthouse Pointe, at 176, the Court of Appeals rejected
DEC's contention that "once it determined that no cleanup was warranted, redevelopment or
reuse of the properties was, by force of this circumstance alone, not complicated' within the
meaning of the statutory definition." The Lighthouse Pointe Court held, at 177, that there
is a low threshold of eligibility for an applicant to enter the BCP program and "the Legislature
intended the definition of the term brownfield site' to be interpreted as broadly as its words
suggest [emphasis added]." Professor David Siegel described the Lighthouse
Pointe decision as petitioner "is sustained and the DEC's position dismissed as so much solid
waste." (Brownfield Cleanup Program, Finding Arbitrary the DEC's Rejection of Owner's
Request to Admit Its Land into Cleanup Program, Court Mandates Acceptance, Siegel, NY
St L Dig No. 604, at 3 [April 2010]). The Appellate Division, First Department in East River
Realty Co., LLC, at 564, held, "[w]e reject respondent's [DEC's] argument that a property
may be deemed ineligible for the program on the ground that it would have been remediated in
any event." In Destiny USA Dev., LLC, at 1570, the Appellate Division, Fourth
Department, refused to accept DEC's position because:
The DEC did not address in its determination any of the specified
complications to redevelopment that Destiny asserted would result
from contaminants in the subject parcels. Instead, the DEC relied
upon its self-promulgated "guidance" and "guide factors" that require,
inter alia, consideration of whether a parcel is "idled, abandoned or
underutilized" and a comparison of the estimated remediation cost "to
the anticipated value of the proposed site as redeveloped or reused."
Those factors effectively limit inclusion in the BCP to parcels of real
property that, but for BCP participation, would remain undeveloped.
[*8] We conclude that the application of such a categorical
limitation without
a fact-specific analysis contravenes the broadly worded definition of
brownfield site set forth in ECL 27-1402 (2) . . . Thus, the categorical
application by the DEC of its "guidance" and "guide factors" as a
precondition to admission into the BCP both conflicts with the intent
of the Legislature and constitutes an impermissible attempt to legislate.
In the instant proceeding, similar to Lighthouse Pointe, DEC's interpretation of the
"complication of development" tests goes against the statutory requirement that the definition of
a "Brownfield site" be construed as broadly as the language in ECL § 27-1405 (2) suggests.
Thus, DEC's internal determination and formal denial of petitioner
Next, DEC found that estimated cost of any necessary remedial program was likely to be
insignificant in comparison to the anticipated value of the proposed site as redeveloped or reused
[AR at 1611]. DEC's analysis was flawed. It failed to account for petitioner's alleged inability to
obtain financing absent its participation in the BCP [Spitler Affidavit, ¶ 9 and ¶ 11].
DEC accorded no weight to the two remaining DEC "complication of development" test
factors which were satisfied, underutilization of the Site and the Site's location in a blighted area.
Also, DEC did not consider other socio-economic factors such as the number of new
construction jobs that would be created for the duration of the project and future additional
property taxes collected as a result of the project. DEC in its formal denial, eschewed applying its
own Eligibility Guidance Manual § 2.2.3 "complication of development" factors.
The Court of Appeals, as noted above, held in Lighthouse Pointe, that DEC's narrow
interpretation of the "complication of development" test for a subject property to be eligible for
the inclusion in the BCP was overly restrictive and not supported by the language of the statute
or the legislative intent. The Lighthouse Pointe Court rejected DEC's argument that it
was the sole arbiter to determine whether or not a site should be included in the BCP, instructing
in Lighthouse Pointe at 177, "that the Legislature intended the definition of the term
brownfield site' to be interpreted as broadly as its words suggest." The Lighthouse Pointe
holding, reversed the Appellate Division's decision to the contrary (61 AD3d 88 [4d Dept 2009]),
which accorded deference to DEC, and reinstated the order of the Supreme Court, Monroe
County (2007 WL 5540594), which granted petitioner Lighthouse Pointe Property Associates,
LLC's Article 78 petition for admission to the BCP. Lighthouse Pointe sends a clear
message to DEC. There must be transparent administration of the BCP, using quantitative
parameters (i.e., the SCOs) to guide decision-making related to the "complication of
development" test, rather than relying exclusively on qualitative, site-by-site determinations.
Thus, DEC, in the instant proceeding, engaged in the same type of sui generis inquiry
rejected by the Court of Appeals in Lighthouse Pointe. DEC used a combination of four
arguments to deny the instant application: (1) the quantitative criteria of the generally accepted
cleanliness levels (the SCOs) were not relevant at the application stage; (2) even if such
quantitative criteria were relevant, they were not meaningful because the site samples did not
significantly exceed them; (3) even if such quantitative criteria were relevant and meaningful,
they could still be disregarded because contamination was located in historic fill material; and
(4), some vague qualitative factors such as "specific site conditions," "the project's design
specifications," and "other methods for eliminating the threats, if any, posed by the presence of
contamination"
DEC's determination in the instant matter, similar to DEC's determination in Lighthouse
Pointe was arbitrary and capricious or an abuse of discretion, for the following reasons:
(1)The generally accepted cleanliness levels, or the SCOs,
represent the only objective, "hard" data indicating whether
a site is contaminated. The SCOs must be used at the
application stage in order for the DEC's decision-making to
[*10] be rational and transparent;
(2)The contamination of the Site is meaningful because, based
upon lead data samples alone of the thirteen initial borings in
the fill, the composite samples in three, or 23%, of the borings
exceeded the restricted residential SCO level of 400 ppm
for lead [Gavras Affidavit, ¶ 35]. Sixteen of the twenty-seven
supplemental soil samples that were collected for total lead
analyses, or 59%, exceeded the SCO level for lead [Gavras
Affidavit, ¶ 32]. DEC admitted, in its formal denial, that there
were seven separate toxins present at the site in concentrations
that exceeded the maximum allowable levels of various
contaminants that can be present at a BCP site after a cleanup
is completed [AR at 1616];
(3)The alleged location of the contamination in the historic fill
material at the site did not negate the fact that the site is
contaminated; and
(4)DEC ignored petitioner's alleged inability to obtain financing
absent its participation in the BCP [Spitler Affidavit, ¶ 9 and
¶ 11].
In my May 3, 2010 decision and order, I held that the record was incomplete and ordered: (1)
further groundwater and soil vapor investigation; (2) a magnetometer survey of the site; (3)
documentation of petitioner's efforts to obtain financing beyond the allegations in the Spitler
affidavit; and, (4) petitioner FLATBUSH to provide DEC for its consideration with information
whether or not petitioner FLATBUSH would be able to proceed with the project unless the Site
is accepted into the BCP.
A motion for leave to
reargue "shall be based upon matters of fact or law allegedly overlooked or misapprehended by
the court in determining the prior motion, but shall not include any matters of fact not offered on
the prior motion." (CPLR Rule 2221 [d] [2]).
The Court, upon reargument, now finds that: the information submitted by petitioner
FLATBUSH in the Gavras affidavit to respondent DEC was substantially similar to that
submitted by the petitioner in Lighthouse Pointe; and, the AR was sufficiently developed
to have determined that the Site was eligible for immediate admission into the BCP without the
need for supplemental information. Petitioner's original application, containing information
related to multiple contaminants in the soil, was sufficient evidence that the Site met the
brownfield site statutory definition. "Real property qualifies as a brownfield site" for purposes of
acceptance into the BCP as long as the presence or potential presence of a contaminant within its
boundaries makes redevelopment or reuse more complex, involved, or difficult in some way."
(Lighthouse Pointe at 177).
Moreover, my May 3, 2010 condition requiring petitioner FLATBUSH to provide DEC with
evidence of financing complications was unnecessary. Contaminant levels exceeding regulatory
standards inherently create complications related to soil disposal which is sufficient for the Site
to be admitted into the BCP. The Court of Appeals, in Lighthouse Pointe, at 177, held
that "complicate," which is undefined in the statute, "in common English usage means to make
complex, involved or difficult' . . . Accordingly, real property qualifies as a brownfield site' for
purposes of acceptance into the BCP so long as the presence or potential presence of a
contaminant within its boundaries makes redevelopment or reuse more complex, involved or
difficult in some way [emphasis added]." As such, the Court of Appeals did not
limit the term "complicate" to simply being unable to obtain financing. Petitioner FLATBUSH
submitted sufficient information to the Court to determine that redevelopment of the Site was
complicated by contamination based upon the AR and the Spitler affidavit.
Further, my last condition that petitioner FLATBUSH provide DEC with information
whether or not petitioner FLATBUSH would be able to proceed with the project unless it was
accepted into the BCP is a "but for" test, which should not have been required. In Therefore, with the grant of reargument to petitioner FLATBUSH, the Site is admitted
forthwith into the BCP.
Article 86 of the CPLR, the "New York State Equal Access to Justice Act," provides, [*12]according to CPLR § 8600 "a mechanism authorizing the
recovery of counsel fees and other reasonable expenses in certain actions against the state of New
York, similar to the provisions of federal law contained in 28 U.S.C. § 2412 (d) and the
significant body of case law that has evolved thereunder." Petitioner FLATBUSH is granted an
award of its costs, disbursements, legal and other fees, which resulted in my May 3, 2010
decision and order and this motion to reargue, provided it files an application with this Court
complying with the requirements of CPLR § 8601.
Accordingly, it is
ORDERED, that the motion of petitioner 29 FLATBUSH AVENUE
ORDERED, this Court continues to hold that respondent ORDERED, that this Court continues to hold that the aforementioned April 28, 2009
determination of respondent ORDERED, that petitioner 29 FLATBUSH AVENUE ASSOCIATES, LLC's Site, located at
29 Flatbush Avenue, Brooklyn, New York (Block 2105, Lot 19, County of Kings) is admitted
forthwith into the New York State Brownfield Cleanup Program, pursuant to Environmental
Conservation Law § 27-1401 et seq.; and it is further
ORDERED, that petitioner 29 FLATBUSH AVENUE ASSOCIATES, LLC is granted an
award of its costs, disbursements, legal and other fees, which resulted in my May 3, 2010
decision and order and this motion to reargue, pursuant to CPLR Article 86, provided that
petitioner 29 FLATBUSH AVENUE ASSOCIATES, LLC shall comply with the requirements of
CPLR § 8601 by submitting an application to this Court.
ENTER
________________________________
HON. ARTHUR M. SCHACK
J. S.C.
proceeding to: annul and reverse DEC's denial of its BCP application; declare the
Site eligible for the BCP; declare that DEC's March 2005 Eligibility Guidance Manual or any
other informal guidance or policy excluding consideration of the Site from eligibility for the BCP
fatally inconsistent with statutory law, illegal and void; declare that petitioner should be treated
equally with all other parties in the BCP; and, direct respondents to grant petitioner's application
to participate in the BCP for remediation and redevelopment of the Site. Respondent DEC
opposed the petition and included, as part of its opposition, affidavits from DESNOYERS and
Robert J. Cozzy, DEC Environmental Engineer and Acting Bureau Director for a Remedial
Bureau in the Division of Environmental Remediation. Petitioner replied with affidavits from
John M. Gavras, a certified professional geologist, and Drew Spitler, Vice President of
Development for The Dermot Company, Inc., who manages the Site for petitioner.
(BCPA), effective October 7, 2003, codified in ECL § 27-1401 et seq.
ECL § 27-1405 (2) defines a "Brownfield site," with certain exceptions not relevant in this
proceeding, as "any real property, the redevelopment or reuse of which may be complicated by
the presence or potential presence of a contaminant." Further, ECL § 25-1405 (7-a) defines
"contaminant" as "hazardous waste and/or petroleum as such terms are defined in this section."
Brownfield sites often present, in addition to environmental and blight concerns, legal and
financial burdens. Contaminated sites, particularly when left vacant, diminish property values of
the surrounding area and threaten the economic viability of adjoining properties. The BCPA is to
encourage voluntary cleanup of hazardous waste sites and the ultimate restoration of such sites to
productive use, including restoration to the tax rolls. (Weinberg, Practice Commentaries, [*3]McKinney's Cons Laws of NY, Book 17½, ECL §
27-1401 [2007]).If a BCP applicant satisfactorily cleans a contaminated Brownfield site and
receives DEC's certificate of completion, the applicant can receive tax credits,
pursuant to Tax Law §§ 21-23 and a release from future liability to New York State for
contamination, pursuant to ECL § 27-1421 (1), which "shall run with the land," pursuant to
ECL § 27-1421 (3).
documents of general applicability which are to be relied upon by department
personnel for implementation of this chapter, and rules and regulations promulgated pursuant
thereto, and for guidance to the general public in complying with the requirements of this
chapter." (ECL § 3-0301 [2] [z]). DEC issued: in May 2004, a "Draft Brownfield Cleanup
Program Guide," which has not been finalized to date [the Draft BCP Guide]; and in March
2005, its final Eligibility Determination Guidance [the Eligibility Guidance Manual], which it
incorporated into the Draft BCP Guide. The Eligibility Guidance Manual lists: five factors, in
§ 2.2.2, relating to the "contamination test" that DEC will consider in "determining whether
there is confirmed contamination or a reasonable basis to believe that contamination is likely to
be present on the property"; and, four factors, in § 2.2.3, relating to the "complication of
development test" that DEC will consider in "determining whether there is a reasonable basis to
believe that the contamination or potential contamination may be complicating the development,
use or re-use of the property."
procedures as may be necessary, convenient or desirable to effectuate the purposes of
this chapter." (ECL § 3-0301 [2] [m]). Thus, DEC adopted regulations relating to and
implementing the BCPA. (6 NYCRR § 375-3.1 et seq.). However, DEC's guidance
factors are "conspicuously missing from the DEC's own regulations with regard to the BCP
(see 6 NYCRR Part 375)." (HLP
Props., LLC v New York State Dept. of Envtl. Conservation, 21 Misc 3d 658, 670 [Sup
Ct, New York County 2008], affd 70 AD3d 469 [1d Dept 2010]. DEC's use of its far
more limiting BCP eligibility guidelines for BCP applicants have been rejected by Courts. " [A]n
agency, by law, is not allowed to legislate' by adding guidance requirements' not expressly
authorized by statute.' (Matter of HLP
Props., LLC v New York State Dept of Envtl. Cons., 21 Misc 3d 658, 669; see
Matter of Medical Society of State of New York v Serio, 100 NY2d 854, 866 [2003])." (Destiny USA Development, LLC v New
York State Dept. of Environmental Conservation, 63 AD3d 1568, 1570 [4d Dept 2009],
lv denied 66 AD3d 1502 [4d Dept 2009], lv denied 14 NY3d 703 [2010]).
parking lot since the 1960s [AR at 8, 849]. When the Site was a
parking lot, automotive lifts with hydraulic lift systems were utilized for parking [AR at 8, 849].
Prior to the 1960s, the Site had been the location of a theater [AR at 8] and earlier, prior to the
1900s, the Site had been improved with numerous multistory residential buildings [AR at 38].
The Site is located in Kings County Census Tract 33, which, according to the 2000 US
government census, had a poverty rate of 19.88%.
80% market-rate housing, 20% low-income housing,
some retail units on the ground floor
and underground parking [AR at 11]. To participate in the BCP, petitioner filed, on
April 4, 2008, an application with DEC [AR at 2], initially supported by two reports from
petitioner's environmental consultants [AR at 12]: a Phase I Environmental Site Assessment by
IVI Due Diligence Services, Inc. [AR at 35-102]; and, a Limited Subsurface Investigation Report
prepared by Hydro Tech Environmental Corp. [AR at 844-906].
a low potential for the excavation and off-site disposal of Site soils ashazardous
wastes. Therefore, it is highly unlikely that the redevelopment
"was made in violation of lawful
procedure, was affected by an error of law, or was arbitrary and capricious or an abuse of
discretion." (CPLR § 7803 [3]). For a reviewing court to find that an agency determination
was arbitrary and capricious or an abuse of discretion it would have to find that the action taken
was without sound basis in reason and without regard to the facts (Matter of Pell v Board of
Educ. of Union School District No.1, 34 NY2d 222, 230-231 [1974]). A rational basis exists
where the determination was " [supported] by proof sufficient to satisfy a reasonable [person], of
all the facts necessary to be proved in order to authorize the determination' (Matter of Pell v
Board of Educ. at 231; see Matter of Weber v Town of Cheekatowaga, 284 NY [377]
at 380 [1940])." (Matter of Ador Realty,
LLC v Division of Housing & Community Renewal, 25 AD3d 128, 139-140 [2d Dept
2005]).
of pure statutory analysis [Emphasis
added]."
FLATBUSH's participation in the BCP is not entitled to any special deference, and is
arbitrary and capricious and an abuse of discretion.
DEC found, in its internal memorandum, dated July 29, 2008, when applying its own
"complication of development" test factors, based upon its Eligibility Guidance Manual §
2.2.3, that two of the four "complication of development" test factors: whether the proposed site
is unattractive for redevelopment or reuse due to the presence or reasonable perception of
contamination; and whether the estimated cost of any necessary remedial program is likely to be
significant in comparison to the anticipated value of the
proposed site as redeveloped or reused; weighed against petitioner [AR at
1610-1611].
DEC considered, in its formal April 28, 2009 denial of petitioner's BCP
application, "whether there is a reasonable basis to believe that such contamination
or potential contamination may complicate the redevelopment or reuse of the property" [AR at
1615]. While taking it as a given that the Site was contaminated with seven separate types of
toxins, as well as lead, all in excess of DEC's regulatory remediation objectives, DEC
nevertheless concluded that petitioner's multiple soil "sampling results do not indicate that there
will be anycomplications of the Site's future development as the contamination [sic]"[AR at
1616]. DEC claimed that contamination samples were few in number, widely separated, and not
of enough magnitude, even though the readings at the site exceeded its own published
contamination levels [AR at 1616]. To discount these contamination readings, DEC asserted that
only seven out of the total of nineteen toxins [*9]found exceeded
the contamination levels [AR at 1616]. Therefore, according to DEC, the Site having an
excessive amount of seven separate toxins is insufficient to complicate the Site's development,
even though ECL § 27-1405 (2) only requires the "presence or potential presence of
a contaminant [emphasis added]." Also, DEC brushed aside the presence of a
sample with an extremely high lead concentration as a fluke, claiming that "the lead sample
appears to be isolated due to the lack of similar sampling results both in proximity of the sample
in question or elsewhere on the Site" [AR at 1616].
[Cozzy Affidavit, ¶ 15] weighed in favor of denying the application.
"A motion for reargument, addressed to the discretion of the court, is designed to
afford a party an opportunity to establish that the court overlooked or misapprehended the
relevant facts, or misapplied any controlling principle of law. Its purpose is not to serve as a
vehicle to permit the unsuccessful party to argue once again the very questions previously
decided." (Foley v Roche, 68 AD2d 558, 567 [1d Dept 1979]). "[T]he determination to
grant leave to reargue a motion lies with the sound discretion of the court." (Anthony J.
Carter, DDS, P.C. v Carter, 81 AD3d 819 [2d Dept 2011]). (See Spectrum Painting Contractors, Inc. v
Kreisler Borg Florman General Const. Co., Inc., 54 AD3d 748, 749 [2d Dept 2008]; Vishnevsky v Glassberg, 29 AD3d
680, 681 [2d Dept 2006]; McGill v Goldman, 261 AD2d 593, 594 [2d Dept 1999]).
The Court now finds that it misconstrued certain limited issues in its May 3, 2010 decision and
order, and in its discretion, pursuant [*11]to CPLR Rule 2221 (d)
(2), grants leave to petitioner FLATBUSH to reargue those portions of my May 3, 2010 decision
and order that it alleges the Court misapprehended.
Conclusion
ASSOCIATES, LLC to reargue, pursuant to CPLR Rule 2221 (d), certain limited
issues in my May 3, 2010 decision and order in this Article 78 proceeding, published at 27 Misc
3d 1217 (A), is granted; and it is further