| Johnson v Commercial Constr. Tech., Inc. |
| 2012 NY Slip Op 50422(U) [34 Misc 3d 157(A)] |
| Decided on March 6, 2012 |
| Appellate Term, Second Department |
| Published by New York State Law Reporting Bureau pursuant to Judiciary Law § 431. |
| This opinion is uncorrected and will not be published in the printed Official Reports. |
Appeal, on the ground of inadequacy, from a judgment of the District Court of Suffolk
County, Third District (C. Stephen Hackeling, J.), entered August 23, 2010. The judgment, after
a nonjury trial, awarded plaintiff the principal sum of $78.
ORDERED that the judgment is modified by providing that the award in favor of plaintiff is increased by $705 to the principal sum of $783; as so modified, the judgment is affirmed, without costs.
Plaintiff commenced this small claims action to recover $5,000 from defendant for failure to complete work under a $30,000 home improvement contract, for overcharging her and for property damage. Defendant interposed a counterclaim to recover, among other things, the sum of $705 as the balance due on the contract. After a nonjury trial, the District Court found that plaintiff was due a total of $783, which sum was offset by $705, the amount plaintiff owed on the contract. Consequently, a judgment was entered in favor of plaintiff in the principal sum of $78.
The decision of a fact-finding court should not be disturbed upon appeal unless it is obvious that the court's conclusions could not be reached under any fair interpretation of the evidence (see Claridge Gardens v Menotti, 160 AD2d 544 [1990]). This standard applies with [*2]greater force to judgments rendered in the Small Claims Part of the court (see Williams v Roper, 269 AD2d at 126).
Upon a review of the record, we conclude that the judgment did not provide the parties with substantial justice according to the rules and principles of substantive law (UDCA 1804, 1807; see Ross v Friedman, 269 AD2d 584 [2000]; Williams v Roper, 269 AD2d 125, 126 [2000]). While most of plaintiff's contentions on appeal lack merit, we find that the District Court erred in determining that plaintiff still owed defendant a balance of $705 on the contract. Plaintiff had submitted into evidence a signed final invoice by defendant's owner, in which he agreed to accept the sum of $3,645 as the final balance due on the contract, rather than the final balance initially specified of $4,350. Accordingly, the principal amount of the judgment awarded to plaintiff should be increased by $705 to the principal sum of $783.
Nicolai, P.J., LaCava and Iannacci, JJ., concur.
Decision Date: March 06, 2012