Lipco Elec. Corp. v ASG Consulting Corp.
2014 NY Slip Op 03236 [117 AD3d 687]
May 7, 2014
Appellate Division, Second Department
Published by New York State Law Reporting Bureau pursuant to Judiciary Law § 431.
As corrected through Wednesday, July 2, 2014


[*1]
 Lipco Electrical Corp. et al., Appellants,
v
ASG Consulting Corporation et al., Respondents. (Action No. 1.) ASG Consulting Corp. et al., Respondents, v Action Electrical Cont. Co., Inc., Also Known as Action Electrical Contracting Company, Inc., et al., Appellants. (Action No. 2.)

Levy, Tolman & Costello, LLP, New York, N.Y. (Robert J. Costello of counsel), for appellants.

Robinson Brog Leinwand Greene Genovese & Gluck, P.C., New York, N.Y. (Felicia S. Ennis and Alan M. Pollack of counsel), for respondents.

In two related actions, inter alia, to recover damages for breach of contract, the plaintiffs in action No. 1 and the defendants in action No. 2 appeal from an order of the Supreme Court, Nassau County (Driscoll, J.), entered February 2, 2012, which denied their motion for summary judgment dismissing the complaint in action No. 2, pursuant to CPLR 3126 to strike the defendants' answer in action No. 1, and for an award of sanctions based on the spoliation of evidence.

Ordered that the order is affirmed, with costs.

"[A] contract entered into in violation of a statute is an unlawful undertaking and such an illegal contract cannot give rise to a viable cause of action" (Scotto v Mei, 219 AD2d 181, 183 [1996]; see Carmine v Murphy, 285 NY 413, 416 [1941]; Parpal Rest. v Martin Co., 258 AD2d 572, 573 [1999]). On that branch of the appellants' motion which was for summary judgment dismissing the complaint in action No. 2, the appellants failed to demonstrate their prima facie entitlement to judgment as a matter of law since their evidentiary submissions did not establish that the contracts from which the causes of action in action No. 2 arise are illegal. The appellants assert that the subject contracts are illegal because ASG Consulting Corp. (hereinafter ASG), a plaintiff in action No. 2, is a successor to TAP Electrical Consulting Service, Inc. (hereinafter TAP), also a plaintiff in action No. 2, and that at the time the subject contracts were formed, TAP and its successors were rendered ineligible to bid on or be awarded any public works contracts pursuant to Labor Law former § 220-b (3) (b). There remains a triable issue of fact as to whether ASG is a "successor" to TAP within the meaning of Labor Law former § 220-b (3) (b), thereby rendering illegal the contracts upon which action No. 2 is based (see generally Alvarez v Prospect Hosp., 68 NY2d 320 [1986]). Accordingly, the Supreme Court [*2]properly denied that branch of the appellants' motion which was for summary judgment dismissing the complaint in action No. 2.

The Supreme Court also properly denied those branches of the appellants' motion which were pursuant to CPLR 3126 to strike the answer of the defendants in action No. 1 and for an award of sanctions based on the spoliation of evidence, since the appellants failed to conclusively establish that certain evidence was "willfully destroyed or discarded in order to frustrate [their] interests" (Cohen v Jordan Servs., Inc., 49 AD3d 680, 681 [2008]; see Falcone v Karagiannis, 93 AD3d 632, 633-634 [2012]). Dillon, J.P., Hall, Cohen and Hinds-Radix, JJ., concur. [Prior Case History: 2012 NY Slip Op 30370(U).]