| Board of Mgrs. of 550 Grand St. Condominium v Schlegel LLC |
| 2014 NY Slip Op 50576(U) [43 Misc 3d 1211(A)] |
| Decided on April 4, 2014 |
| Supreme Court, Kings County |
| Schmidt, J. |
| Published by New York State Law Reporting Bureau pursuant to Judiciary Law § 431. |
| This opinion is uncorrected and will not be published in the printed Official Reports. |
The Board of
Managers of 550 Grand Street Condominium, suing on behalf of its constituent unit
owners, Plaintiff,
against Schlegel LLC, 550 Grand LLC, EcoRise Development LLC, Ghattas Engineering PLLC (f/k/a Duke + Ghattas Associates LLC), Eco-Build Construction (f/k/a L-Line Enterprises, Inc.), Timothy Phillips, Michael T. Schlegel, and Cynthia A. Schlegel,, Defendants. |
Plaintiff Board of Managers of 550 Grand Street Condominium
(plaintiff) commenced this action on behalf of the unit owners to recover compensatory
and punitive damages allegedly sustained as a result of purported defects in the
renovation a four-storey, mixed-use walk-up building at 550 Grand Street in the
Williamsburg section of Brooklyn (the building). Its first amended complaint, dated Aug.
27, 2013 (the complaint), asserts claims for, inter alia, breach of express and implied
warranties, negligent construction/supervision, fraud/misrepresentation, violation of
General Business Law §§ 349-350, breach of contract, negligence, and breach
of contract/third-party beneficiary (the second, third, fourth, fifth, sixth, seventh, eighth,
and tenth causes of action, respectively). The complaint named as defendants the sponsor
550 Grand (the sponsor); the developer EcoRise Development LLC (the developer); the
contractor Eco-Build Construction, formerly known as L-Line Enterprises, Inc. (the
contractor); the sponsor's managing partner and general manager Schlegel LLC; and the
architect and engineer Ghattas Engineering PLLC, formerly known as Duke + Ghattas
Associates LLC (the architect); and the sponsor's members Michael T. Schlegel and
Cynthia A. Schlegel (the Schlegels), together Timothy Phillips (Phillips). The Schlegels
were also the members of the developer and Schlegel LLC, whereas Philips was the
contractor's principal and founding member. The sponsor, the developer, the contractor,
Schlegel LLC, and the Schlegels (collectively, the Schlegel defendants) move,
pre-answer, for an order, pursuant to CPLR 3211 (a) (1), (3), and (7), dismissing certain
causes of actions as against some or all of them, as applicable, and to dismiss the action
in its entirety against Schlegel LLC and each of the Schlegels (Seq. No. 1). The architect
moves, pre-answer, for an order, pursuant to CPLR 3211 (a) (1), (5), and (7), dismissing
the complaint against it (Seq. No. 2). Plaintiff opposes both motions.
The building's six apartments and one commercial space in the building were sold under a condominium offering plan (the offering plan) that was submitted by the sponsor and accepted for filing by the Attorney General's office on July 11, 2008. The offering plan (at pages 7, 23, 51, and 78) included representations by the sponsor that it would renovate the building substantially in accordance with the plans and specifications set forth in the architect's report, and that it applied for a J-51 tax abatement. Additionally, the offering plan (as part of Exhibit J) appended "Certification by Sponsor and Sponsor's Principals," dated June 26, 2008, executed by Michael Schlegel and Phillips individually, and by Cynthia Schlegel both individually and on the sponsor's behalf. The certification recited that each attesting party — after reading the entire offering plan and investigating the facts set forth in the offering plan and the underlying facts — represented that it omitted no [*2]material fact, contained no untrue statement of a material fact, contained no fraud, deception, or concealment, and contained no representation or statement which was false where the certifying party either knew the truth, or with reasonable effort could have known the truth, or made no reasonable effort to ascertain the truth. The certification warned in a paragraph appearing immediately above the signature line that it was made under penalty of perjury for the benefit of all persons to whom the offer was made, and that violations were subject to the civil and criminal penalties of the General Business Law and Penal Law, as required by the Attorney General's regulation at 13 NYCRR 20.4 (b).
The offering plan included the architect's report, entitled the "Description of Property and Specifications," dated Jan. 18, 2008, as amended May 2, 2008, regarding the condition of the building (the architect's report). The architect provided a "Certification by Sponsor's Engineer" (executed by its principal Adib Z. Ghattas, P.E., and annexed to the offering plan as Exhibit K) "for the benefit of all persons to whom this offer [of units] was made." Mr. Ghattas certified that the architect prepared "building plans and specifications approved by the [New York City] Building Department in September . . . 2007 and prepared [the architect's report], a copy of which is intended to be incorporated into the Offering Plan, so that prospective purchasers may rely [on it]." Mr. Ghattas further certified that he read the architect's report in its entirety and investigated with due diligence both the facts stated in it and the facts on which it was based, and that it accurately, truthfully, and completely described the building on completion of construction, assuming that construction was performed in accordance with its plans and specifications. The architect's certification, however, warned that "[t]his statement is not intended as a guarantee or warranty of the physical condition of the property."
Units in the building were sold under a purchase agreement in the form annexed to the offering plan as Exhibit A (the purchase agreement), which incorporated the offering plan. The sponsor covenanted (in § 12 of the purchase agreement) that the construction of the building, units, and materials, equipment and fixtures installed therein is substantially in accordance with the offering plan and the architect's report. The purchase agreement (in § 15 at 10) contained a sunset provision whereby written notice of defects had to be given by a date certain in order to invoke the sponsor's obligations to cure. The purchase agreement (in ¶ 15 at 9-10) also included a purchaser's acknowledgment, which survived the closing, that he or she "has not relied upon any architect's plans, . . . including . . . any relating to the description or physical condition of . . . the Building or the Unit. . . ." The offering plan, in turn, stated (in ¶ 15 at 55) that the architect's statement to the "Sponsor that the Building has been completed substantially in accordance with the [architect's] Plans and Specifications * * * shall neither constitute a representation by [the architect] to the Unit Owners or to the Board of Managers nor give rise to any claim by any Unit Owner or by the Board of Managers against the Sponsor's Architect with respect to completion of construction or defects therein."
The offering plan was amended twice, once in 2009 and once in 2010. The first amendment announced that the plan went effective on Feb. 5, 2009, when the purchase agreement for the building's first unit was executed and delivered. The second amendment advised, among other things, that (1) a final certificate of occupancy, dated Apr. 6, 2009, had been issued; (2) a declaration of condominium was filed on Apr. 17, 2009; (3) the first closing was consummated on Apr. 25, 2009; and (4) three of the six residential units had been sold. Each amendment recited that the [*3]remainder of the offering plan, except for the changes set forth therein, stayed the same.
The complaint alleges (in ¶ 44) that the building suffered, and continues to
suffer, from substantial design and construction defects, inadequate and negligent
workmanship, missing or defective materials, and gross deviations from the architect's
report. The building defects include (according to ¶ 47) "water intrusion, mold
infestation, foundation cracking, floor buckling, fire-safety issues, bulging and saturation
in load bearing walls." The building suffered, among other mishaps, a burst pipe in Jan.
2011, a partial collapse of the drainage system and a light well [FN1] in June 2012, and a roof failure in May
2013 (Complaint ¶ 2). Plaintiff's hired consultants discovered many significant
construction deficiencies, sub-standard conditions, and instances of property damage,
either resulting from design defects or from incomplete or inadequate workmanship
(¶¶ 48-51).
Initially, the Schlegel defendants and the architect separately contend that all claims against them are barred by documentary evidence: the offering plan, the purchase agreements, and, in the case of Schlegel LLC, its operating agreement. A motion to dismiss under CPLR 3211 (a) (1) on the grounds that a claim is barred by documentary evidence is granted where the "documentary evidence" completely refutes the plaintiff's factual allegations, conclusively establishing a defense to such claim as a matter of law (see Goseh v Mutual Life Ins. Co., 98 NY2d 314, 326 [2002]). To qualify as "documentary," evidence must be unambiguous and of undisputed authenticity. Whereas a condominium offering plan has been held to constitute "documentary" evidence (see Board of Mgrs. of Park Slope Views Condominium v Park Slope Views, LLC, 39 Misc 3d 1221[A], 2013 WL 1849128, *7, 2013 NY Slip Op 50689[U] [Sup Ct, Kings County 2013]), it is not "conclusive," since plaintiff is challenging the accuracy of the offering plan itself (see Board of Mgrs. of 14 Hope St. Condominium v Hope St. Partners, LLC, 40 Misc 3d 1215[A], 2013 WL 3814672, *3, 2013 NY Slip Op 51201[U] Park Slope, 2013 WL 1849128, *7).
The Schlegel defendants next contend that Schlegel LLC does not belong in the case.
They assert that Schlegel LLC has been named herein on account of a typographical error
by the sponsor's attorney; that is, a draft condominium declaration, as annexed to the
offering plan, incorrectly named Schlegel LLC as the sponsor. They point out that a final
condominium declaration, as filed with the Office of the City Register, correctly named
550 Grand St LLC as the sponsor and that the operating agreement for Schlegel LLC
restricted its activities to other properties not involving this building. In opposition,
plaintiff, by affidavit of its board member Alana Blahoski, maintains (in ¶ 16) that
Schlegel LLC was part of the Schlegels' corporate empire and that the condominium's
bank records reflected that Michael Schlegel had transferred funds to and from various
other accounts of his and those of his wife Cynthia and Schlegel LLC. More specifically,
Ms. Blahoski cites to a money transfer (transaction #00983766312) between the
condominium and Schlegel LLC. Although the Court accepts the Schlegel defendants'
innocent explanation for the erroneous naming of Schlegels LLC as the sponsor in the
draft condominium declaration, the Court notes that Michael Schlegel has proffered no
affidavit in rebuttal to Ms. Blahoski's contention. Their defense counsel pooh-poohs Ms.
Blahoski's affidavit as ambiguous and lacking in documentary support, while insisting
that the [*4]generic language in the operating agreement
of Schlegel LLC beats her fairly specific affidavit. The Court concludes that the Schlegel
defendants and the architect have failed to meet their heavy burden under CPLR 3211 (a)
(1), and those branches of their respective motions are denied (see Board of Mgrs. of Marke
Gardens Condominium v 240/242 Franklin Ave., LLC, 71 AD3d 935, 936 [2d
Dept 2010]).
As an additional basis for dismissal, the Schlegel
defendants cite to, but do not otherwise discuss, CPLR 3211 (a) (3), which permits
dismissal in the instance where the plaintiff lacks legal capacity to sue. Real Property
Law § 339-dd permits a condominium board of managers to assert on behalf of two
or more unit owners "any cause of action relating to the common elements or more than
one unit." The complaint (in ¶¶ 44, 47, 71-97) alleges numerous defects
affecting the building's common areas, thus satisfying the commonality elements required
by the statute. Hence, the branch of the Schlegel defendants' motion for dismissal under
CPLR 3211 (a) (3) is also denied (see Residential Bd. of Managers of Zeckendorf
Towers v Union Square-14th St. Assoc., 190 AD2d 636, 637 [1st Dept 1993]).
The architect moves for dismissal of the contract and negligence claims against it (the seventh and eighth causes of action) as time-barred. CPLR 214 (6) imposes a three-year statute of limitations for professional malpractice (with certain exceptions not applicable here), "regardless of whether the underlying theory is based in contract or tort." A cause of action to recover damages against an architect for professional malpractice accrues upon the work completion and the resulting termination of the architect's professional relationship with its client (see Vlahakis v Belcom Dev., LLC, 86 AD3d 567, 568 [2d Dept 2011]). A client's professional malpractice claim accrues when its architect completes performing significant, non-ministerial contractual duties (see Sendar Dev. Co. v CMA Design Studio P.C., 68 AD3d 500, 503 [2d Dept 2009]). For example, if the architect is contractually required to obtain a certificate of occupancy, the date of the certificate's issuance is the end point of the client's professional relationship with its architect (see Frank v Mazs Group, 30 AD3d 369, 370 [2d Dept 2006]). It is uncontested that this action was commenced on June 7, 2013, which was more than three years after the final certificate of occupancy was issued on Apr. 6, 2009 (Complaint, ¶ 25). Thus, the architect has sustained its initial burden of demonstrating that the contract and negligence claims against it are time-barred (see Regency Club at Wallkill, LLC v Appel Design Group, P.A., 112 AD3d 603, 607 [2d Dept 2013] Willis Ave. Dev., LLC v Block 3400 Constr. Corp., 42 Misc 3d 1223[A], 2014 WL 590211, *2-3, 2014 NY Slip Op 50185[U] [Sup Ct, Kings County 2014]).
In opposition, plaintiff proffers an affidavit of Board member Naomi Azuma,
asserting (in ¶ 12) that "the Unit Owners were informed by the Sponsor that [the
architect] bore [but failed to fulfill its] responsibility for obtaining the J-51 tax exemption
for the Building." Putting aside the obvious hearsay nature of Ms. Azuma's affidavit, it
contradicts plaintiff's complaint (¶¶ 15, 34, 138, 180) and the offering plan
(¶ 10 at 7; ¶ E at 23; page 78), which placed responsibility for applying for
the tax abatement exclusively on the sponsor.[FN2] Ms. Azuma's generalized,
unsubstantiated [*5]affidavit alleging that the architect
was responsible for applying for a J-51 tax abatement is insufficient to rebut the
architect's prima facie showing (see Seymour v New York State Elec. & Gas
Corp., 215 AD2d 971, 972 [3d Dept 1995]).
The CPLR 3211 (a) (7) Defense of Failure to State a Cause
of Action
A motion to dismiss under CPLR 3211 (a) (7) for failure to state a cause of action
may be granted "when the allegations and inferences do not fit within any cognizable
legal theory" (Nadal v
Jaramillo, 102 AD3d 843, 844 [2d Dept 2013]). The court "must accept the
allegations in the complaint as true and accord the plaintiff every possible favorable
inference from them" (id.). "Whether a plaintiff can ultimately establish its
allegations is not part of the calculus in determining a motion to dismiss" (EBC, Inc. v Goldman, Sachs &
Co., 5 NY3d 11, 19 [2005]). In assessing a motion under CPLR 3211 (a) (7), a
court may freely consider a plaintiff's affidavits to remedy any defects in the complaint.
As to a defendant's affidavits, they will almost never mandate dismissal under CPLR
3211, unless they establish conclusively that the plaintiff has no claim (see Moreno v
Future Care Health Servs., Inc., 2014 WL 1236815, *12-13, 2014 NY Slip Op
50449[U] [Sup Ct, Kings County 2014]).
1.Claims Against the Sponsor 550 Grand LLC
Breach of Express and Implied Warranties (Second and Third Causes of
Action)
For its second and third causes of action, the complaint alleges (in ¶¶ 9, 143, and 152) that the sponsor breached its express and implied obligations to "diligently, expeditiously and at [its] own cost, complete the construction of the Units and Common Elements substantially in accordance with the plans and specifications described [in the offering plan]." The sponsor challenges the validity of the warranty claims on the principal ground that these claims are duplicative of the contract claim. The Court finds the warranty claims (the second and third causes of action) and the contract claim (the first cause of action) to be legally identical. To be sure, the complaint throws in phrases such as "express warranty" and "implied warranty" when describing the sponsor's misconduct (Complaint [*6]¶¶ 130, 133, 136, 152, 156).[FN3] The presence, however, of a few conclusory legal terms does not insulate the warranty claims from dismissal as essentially a redundant repleading of the contract claim (see Board of Mgrs. of Woodpoint Plaza Condominium v Woodpoint Plaza LLC, 24 Misc 3d 1233[A], 2009 WL 2432346, *6, 2009 NY Slip Op 51715[U] [Sup Ct, Kings County 2009]).[FN4]
Negligent Construction/Supervision (Fourth Cause of Action)
In a variation on the theme, the complaint alleges (in ¶¶ 163-164 and
166-167) that the sponsor breached its duty to construct, supervise, and manage the
building. Here, the complaint (in ¶ 175) adds punitive damages to the prayer of
relief. Yet, a simple breach of contract is not to be considered a tort unless a legal duty
independent of the contract has been violated. This legal duty must spring from
circumstances extraneous to, and not constituting elements of the contract, although it
may be connected with, and dependent upon, the contract (see Board of Mgrs. of
Riverview Condominium III v Schorr Bros. Dev. Corp., 182 AD2d 664, 666 [2d
Dept 1992]). Plaintiff has failed to establish that the sponsor owed the unit owners a
legal duty of care that was independent of its contractual duty that arose from its
purchase agreements with the unit owners (id.). Tacking on an additional request
for punitive damages to this cause of action does not change the fundamental fact that it
is duplicative of the contract claim (see Metro. Life Ins. Co. v Noble Lowndes Intl.,
Inc., 84 NY2d 430, 435 [1994]). Accordingly, this claim is also dismissed.
[*7]Common-Law Fraud, Deceit, and
Misrepresentation (Fifth Cause of Action)
The complaint's common-law fraud claim arises, for the most part, out of the misrepresentations and omissions of the contents of the purchase agreements and the offering plan. The fraud claim is not preempted by the Martin Act [FN5] because the complaint alleges affirmative misrepresentations, rather than solely omissions (see Caboara v Babylon Cove Dev., LLC, 82 AD3d 1141, 1142 [2d Dept 2011] 14 Hope St. Condominium, 2013 WL 3814672, *4; see also Sutton Apts. Corp. v Bradhurst 100 Dev., LLC, 107 AD3d 646, 648 [1st Dept 2013] Board of Mgrs. of Baxter St. Condominium v Baxter St. Dev., LLC, 2013 NY Slip Op 32742[U] [Sup Ct, NY County 2013]). The fraud claim meets the particularity requirements of CPLR 3016 (b),[FN6] considering that the facts suffice to permit a reasonable inference of the alleged misconduct (see Eurycleia Partners v Seward & Kissel, LLP, 12 NY3d 553, 559 [2009]).
However, the fraud claim against the sponsor fails as a matter of law because it is subsumed in the contract claim. A cause of action to recover damages for fraud does not lie where the only fraud asserted relates to an alleged breach of contract (see Stangel v Chen, 74 AD3d 1050, 1052 [2d Dept 2010]). In other words, a fraud claim fails when an alleged breach of contractual duties and the supporting allegations do not concern representations that are collateral or extraneous to the terms of the parties' agreement (see Yenrab, Inc. v 794 Linden Realty, LLC, 68 AD3d 755, 757 [2d Dept 2009]). Here, the complaint limits the universe of misrepresentations and omissions to only those that are inconsistent with the express terms of the purchase agreements.[FN7] It also lacks supporting allegations that are collateral or extraneous to their express terms. Plaintiff has not alleged, much less proved, the existence of any misrepresentations or omissions by the sponsor that were collateral or extraneous to the express terms of the purchase agreements as incorporated into the offering plan. As noted, plaintiff has not alleged or identified what legal duty the sponsor owed to the prospective purchasers, other than the duty the sponsor owed them under the purchase agreements and the offering plan (see Current Med. Directions, LLC v Salomone, 26 Misc 3d 1229[A], 2010 WL 724686, *8, 2010 NY Slip Op 50315[U] [Sup Ct, NY County 2010]).
It is true that "where the plaintiff pleads that it was induced to enter into a contract based on the defendant's promise to perform and that the defendant, at the time it made the promise, had a preconceived and undisclosed intention of not performing' the contract, such a promise constitutes a representation of present fact collateral to the terms of the contract and is actionable in fraud" [*8](Manas v VMS Assoc., 53 AD3d 451, 453 [1st Dept 2008]). But here the complaint merely alleges (in ¶¶ 40, 190, 193) that the offering plan contained misrepresentations and omissions to induce prospective purchasers to acquire the units in the building. It does not allege than that the sponsor had a "preconceived and undisclosed intention of not performing" under the purchase agreements (see Manas, 53 AD3d at 454).[FN8] It is of no help to plaintiff that the complaint alleges that false statements were made "outside the [offering] plan after [the] Units were purchased" (¶ 180 [emphasis added]). This allegation is not fleshed out by some concrete examples or affidavits, but is buried in a mass of the complaint's repetitive allegations about the offering plan's misrepresentations and omissions.
In substance, therefore, the contract claim and the fraud claim both allege that the
sponsor failed to deliver to plaintiff and the unit owners a well-constructed condominium
with defect-free apartments/common areas and a J-51 tax abatement. The fraud alleged
against the sponsor is based on the same facts that underlie the contract claim, is not
collateral to the contract, and does not call for damages that otherwise would be
unrecoverable under a contract theory (see Laurel Hill Advisory Group, LLC v American Stock Transfer &
Trust Co., 112 AD3d 486, 487[1st Dept 2013]). If anything, a fraud claim
demands a higher burden of proof than a contract claim (see Jo Ann Homes at
Bellmore, Inc. v Dworetz, 25 NY2d 112, 121 [1969]). Hence, the fraud claim against
the sponsor is dismissed as duplicative of the contract claim (see Kestenbaum v
Suroff, 268 AD2d 560, 561 [2d Dept 2000] 14 Hope St. Condominium,
2013 WL 3814672, *5; Board of Mgrs. of Crest Condominium v City View Gardens
Phase II, LLC, 35 Misc 3d 1223 [A], 2012 WL 1660679, *8, 2012 NY Slip Op
508260[U] [Sup Ct, Kings County 2012]).
Deceptive Acts and Practices Under
General Business Law §§ 349-350 (Sixth Cause of Action)
In the sixth cause of action, the complaint alleges (in ¶¶ 201-202) that the sponsor created, [*9]prepared and disseminated "promotional materials, selling brochures and advertisements concerning the Building to consumers," and that the representations contained therein and in the offering plan were false and misleading. Contrary to the sponsor's contention, the Martin Act does not bar claims under General Business Law § 349 or § 350 (see Board of Mgrs. of Bayberry Greens Condominium v Bayberry Greens Assoc., 174 AD2d 595, 596 [2d Dept 1991] Board of Mgrs. of Cobble Hill Condominium v Hicks & Warren, LLC, 14 Misc 3d 1234[A], 2007 WL 556897, *11, 2007 NY Slip Op 50297[U] [Sup Ct, Kings County 2007]).[FN9] Plaintiff's claims under General Business Law §§ 349-350, if otherwise valid, are not preempted by the Martin Act.
Section 349 (h) provides that any person who has been injured by deceptive acts or practices in the conduct of any business may bring an action in his own name to enjoin such unlawful act or practice (see B.S.L. One Owners Corp. v Key Intl. Mfg., Inc., 225 AD2d 643, 644 [2d Dept 1996]). "To state a claim . . ., a plaintiff must allege that the defendant has engaged in an act or practice that is deceptive or misleading in a material way and that plaintiff has been injured by reason thereof. "Whether a representation or an omission, the deceptive practice must be likely to mislead a reasonable consumer acting reasonably under the circumstances," although "[a] deceptive practice . . . need not reach the "level of common-law fraud to be actionable under section 349" (Stutman v Chemical Bank, 95 NY2d 24, 29 [2000] [internal quotation marks omitted]).
False advertising in the conduct of any business is actionable pursuant to § 350, which likewise allows a private right of action (see Solomon v Bell Atlantic Corp., 9 AD3d 49, 52 [1st Dept 2004]). Under § 350, a plaintiff must demonstrate that an advertisement had an impact on consumers at large, was deceptive or misleading in a material way, and resulted in injury. The test is whether the advertisement is likely to mislead a reasonable consumer acting reasonably under the circumstances (see Andre Strishak & Assoc. v Hewlett Packard Co., 300 AD2d 608, 609 [2d Dept 2002]).
Here, the complaint's allegations (in ¶¶ 200-212) of deceptive practices in the advertisement and sale of condominium units are sufficient to state a claim under §§ 349-350 (see 14 Hope St. Condominium, 2013 WL 3814672, *6-7; Board of Managers of Cobble Hill Condominium v Hicks & Warren, 14 Misc 3d 1234[A], 2007 WL 556897, *11-12, 2007 NY Slip Op 50297[U] [Sup Ct, Kings County 2007]). The sponsor, however, contends that plaintiff's claims fall outside the ambit of §§ 349-350 because the presently litigated dispute is unique to the parties at this particular building and does not involve the public at large, citing the First Department's decisions in Sutton Apts. (107 AD3d at 648) and Thompson v Parkchester Apts. Co. (271 AD2d 311, 311-312 [2000]). Plaintiff, in opposition, points out that the Second Department, unlike the First Department, has held that the advertisement and sale of residential apartments is a consumer-oriented transaction within the meaning of §§ 349-350 (see B.S.L. One Owners, 225 AD2d at 644; Bayberry Greens Condominium, 174 AD2d at 596).
The plain import of the complaint is that the sponsor dealt with the unit owners as it
did with any one else who desired to purchase space in this seven-unit building by
furnishing them with a uniform offering plan. A sale of space in the building was not
private in nature or a single-shot transaction. Although only six of the seven units in the
building have been sold, the marketing [*10]campaign
was still directed to the public at large. Thus, plaintiff has satisfied the threshold test in
that the acts of it complains were consumer-oriented in the sense that they affected
similarly situated consumers (see B.S.L. One Owners, 225 AD2d at 644;
Bayberry Greens Condominium, 174 AD2d at 596; Board of Mgrs. of Caton
Ct. Condominium v Caton Dev. LP, 41 Misc 3d 1231[A], 2013 WL 6182944, *10,
2013 NY Slip Op 51951[U] [Sup Ct, Kings County 2013] see also Straaten v 125
Ct. St., NYLJ 1202631188972 [Sup Ct, Kings County, Nov. 25, 2013]).[FN10]
2.Claims Against the Architect Ghattas Engineering PLLC
The claims against the architect (i.e., contract, negligence, and
fraud) largely mirror the insufficient claims against the sponsor; to the extent the claims
against the architect sound in professional malpractice, they are untimely as noted above.
In addition, these claims fail to state a cause of action. The contract claim, which is based
on the architect's description of the building's condition in the architect's plan as included
in the offering plan and subsequently incorporated in the purchase agreements, is
contradicted by the "no representations" and related disclaimer provisions in the purchase
agreement, the offering plan,[FN11] and the architect's certification (see Board of Mgrs. of Chelsea 19
Condominium v Chelsea 19 Assoc., 73 AD3d 581 [1st Dept 2010]). The
complaint pleads no facts indicating that plaintiff or the unit owners were in privity with
the architect. The agreement between the architect and the sponsor, dated June 20, 2007,
does not reflect an intent that the unit owners be its beneficiaries. Hence, the contract
claim against the architect is dismissed (see Sutton Apts., 107 AD3d at 649;
Kerusa Co. LLC v W10 Z/515 Real Estate L.P., 50 AD3d 503, 504 [1st Dept
2008] Board of Mgrs. of NV 101 N 5th St. Condominium v Morton, 39 Misc 3d
1212[A], 2013 WL 1629239, *8, 2013 NY Slip Op 50575[U] [Sup Ct, Kings County
2013]).
All of the fraud and related tort claims against the architect arise from the same
provisions said to have been breached and seek the same damages, and thus merely
duplicate the insufficient contract claim. Equally unavailing is plaintiff's negligent
misrepresentation claim alleging that the architect, by virtue of its expertise, owed a
special duty to unit purchasers. Although liability for negligent misrepresentation has
been imposed on those persons who possess unique or specialized expertise, or who are
in a special position of confidence and trust with the injured party, the plaintiff's reliance
on the negligent misrepresentation must be justified (see CMMF, LLC v J.P. Morgan Inv. Mgt., Inc., 78 AD3d
562, 656 [1st Dept 2010]). Here, plaintiff's reliance is negated by the provision in
the purchase agreement (in § 15 at 9-10) that each unit purchaser has "relied on his
[or her] own examination and investigation [of the building and the unit]." Moreover, a
cause of action alleging negligent misrepresentation requires the "existence of a special
or privity-like relationship imposing a duty on the defendant to impart correct
information to the plaintiff" (J.A.O. Acquisition Corp. v Stavitsky, 8 NY3d 144, 148
[2007], reargument denied 8 NY3d 939 [2007]). [*11]Here, the negligent misrepresentation and other tort claims
against the architect fail for lack of contractual privity or the functional equivalency of
privity (see Sutton Apts., 107 AD3d at 648). Moreover, plaintiff fails to point to
any specific actions or inactions on the architect's part that caused the complained-of
defects in the building, nor does it offer an expert affidavit to correct this pleading
deficiency (see Board of Mgrs. of NV 101 N 5th St. Condominium, 2013 WL
1629239, *10). The architect's motion is granted, and the complaint insofar as asserted
against it is dismissed in its entirety (see Board of Mgrs. of One Grand Army Plaza v
Seventeen Dev. LLC, 40 Misc 3d 1237[A], 2013 WL 4766515, *5-7, 2013 NY Slip
Op 51465[U] [Sup Ct, Kings County 2013]).
3.Claims Against the Sponsor's Principals, Michael and Cynthia
Schlegel
The complaint (in ¶ 9) defines the term
"Sponsor" to include its sponsor's principals, the Schlegels.[FN12] By doing so, the complaint
generically asserts the same causes of action against the Schlegels as it does against the
sponsor 550 Grand LLC. The claims against the Schlegels sound in contract, express and
implied warranties, negligent construction/supervision, fraud, and General Business Law
§§ 349-350 (the first, second, third, fourth, fifth, and sixth causes of action,
respectively). The preceding analysis of these claims against the sponsor applies,
mutatis mutandis, to the Schlegels. Thus, the claims grounded in express and
implied warranties, negligent construction/supervision, and fraud (the second, third,
fourth, and fifth causes of action, respectively) are dismissed. As to the remaining claims
against the Schlegels sounding in breach of contract and violation of General Business
Law §§ 349-350 (the first and sixth causes of action, respectively), these
claims survive because the Schlegels individually executed and delivered the sponsor's
certification (see Birnbaum v Yonkers Contr. Co., 272 AD2d 355, 357 [2d Dept
2000] Zanani v Savad, 228 AD2d 584, 585 [2d Dept 1996] Zeckendorf
Towers, 190 AD2d at 637-638; 14 Hope St. Condominium, 2013 WL
3814672, *3).
4.Claims Against Schlegel LLC and the Developer EcoRise
Development LLC
At the risk of sounding repetitive, the Court notes that the complaint broadly defines
the term "Sponsor" to include both Schlegel LLC (an entity owned by the Schlegels) and
the developer EcoRise Development LLC. The complaint asserts the same causes of
action against Schlegel LLC and the developer as it does against the sponsor, except in
one instance where it alleges (in ¶ 114), upon information and belief, that the
sponsor converted condominium funds for non-condominium use by using, among other
things, bank accounts in the name of each of Schlegel LLC and the developer. A
supporting affidavit by Board member Alana Blahoski states (in ¶ 16) that the
condominium's bank account reflects a money transfer (transaction #00983766312)
between Schlegel LLC and the condominium, as well as another money transfer
(transaction #00667769137) between the developer and the condominium. As a Board
member, Ms. Blahoski explains (in ¶¶ 15-16 of her affidavit) that "[a]fter the
Board began looking into [the] building finances, the Board began to believe that assets
and resources of the corporate entities and the Schlegels were commingled and
indistinct" and that "Michael Schlegel had transferred funds to and from various other
accounts of his and his Cynthia's as well as Defendant Schlegel, LLC's." As a building
resident, Ms. Blahoski also observed (in ¶ 7) that "Michael Schlegel, Schlegel
LLC, Cynthia Schlegel and EcoRise Development LLC [the developer], . . . and 550
Grand, LLC all had operated [*12]out of the Commercial
Unit Space located next door to [her unit] at [the building]." Notwithstanding the
allegation of potentially questionable transfers (in ¶ 114 of the complaint) and the
supplemental allegations in Ms. Blahoski's affidavit, plaintiff does not have a cause of
action against either Schlegel LLC or the developer. The alleged commingling of funds
and fraudulent money transfers have nothing to do with plaintiff's case-in-chief that the
building and its units are of poor quality. Thus, all claims against Schlegel LLC and the
developer are dismissed with leave to amend to replead claims against these entities, as
more fully set forth in the decretal paragraphs below (see Philips Intl. Invs., LLC v
Pektor, 2012 NY Slip Op 33493[U] [Sup Ct, NY County 2012], renewal denied
on other grounds 2013 NY Slip Op 31233[U], affd 2014 NY Slip Op 01700
[1st Dept 2014]).
5.Claims Against the Contractor Eco-Build Construction
As to this defendant, the complaint asserts a contract claim resting upon the allegations (in its tenth cause of action in ¶¶ 247, 252-253) that the unit purchasers qualified as third-party beneficiaries of a contract between the sponsor and the developer. The complaint additionally asserts (in ¶¶ 247-248) that the developer undertook to manage the renovation of the building and breached its contractual obligations by failing to renovate it in accordance with "proper architectural and engineering plans, specifications, practices and techniques, prevailing local standards and in compliance with relevant codes, rules and ordinances."
An ordinary construction contract — i.e., one which does not
expressly state that the intention of the contracting parties is to benefit a third party
— does not give third parties who contract with the promisee the right to enforce
the latter's contract with another, and such third parties are generally considered mere
incidental beneficiaries (see Board of Mgrs. of Riverview v Schorr Bros. Dev.
Corp., 182 AD2d 664, 665 [2d Dept 1992]). Here, in opposition to plaintiff's
allegations that it is a third-party beneficiary of the sponsor's contract with the developer,
Michael Schlegel avers (in ¶ 10 of his affidavit, dated Sept. 24, 2013) that there
was no written contract between the sponsor and the contractor, "since these entities were
related." Mr. Schlegel's blanket denial fails to establish conclusively that plaintiff
possesses no contract claim against the contractor, and this cause of action against the
contractor survives the motion to dismiss (see Lawrence v Graubard Miller, 11 NY3d 588, 595-596
[2008]).[FN13]
In Seq. No. 2, it is hereby
ORDERED that the branch of the Schlegel defendants' motion to dismiss plaintiff's express warranty, implied warranty, negligent construction/supervision, and fraud claims against the sponsor 550 Grand Street LLC (the second, third, fourth, and fifth causes of action) is granted, and such [*13]claims against the sponsor 550 Grand Street LLC are dismissed; and it is further
ORDERED that the branch of the Schlegel defendants' motion to dismiss plaintiff's claim for deceptive acts and practices under General Business Law §§ 349-350 against the sponsor 550 Grand Street LLC (the sixth cause of action) is denied; and it is further
ORDERED that the branch of the Schlegel defendants' motion to dismiss plaintiff's claims grounded in express and implied warranties, negligent construction/supervision, and fraud (the second, third, fourth, and fifth causes of action, respectively) against Michael T. Schlegel and Cynthia A. Schlegel is granted, and such claims against these individuals are dismissed; and it is further
ORDERED that the branch of the Schlegel defendants' motion to dismiss the remaining claims against Michael T. Schlegel and Cynthia A. Schlegel sounding in breach of contract and violation of General Business Law §§ 349-350 (the first and sixth causes of action, respectively) is denied; and it is further
ORDERED that the branch of the Schlegel defendants' motion to dismiss plaintiff's claims against Schlegel LLC and EcoRise Development LLC is granted, and all such claims against this entity are dismissed; provided, however, that plaintiff is hereby granted leave to file and serve an amended complaint so as to replead its claims, if any, against either or both of these entities within 20 days after service on plaintiff's counsel of a copy of this order with notice of entry (service of an amended complaint must be accompanied by a blackline against the existing complaint); and it is further
ORDERED that if plaintiff fails to serve and file an amended complaint in conformity herewith within such time, then leave to replead shall be deemed denied without further order of the Court, and the defendants 550 Grand LLC, Eco-Build Construction, Michael T. Schlegel, and Cynthia A. Schlegel shall serve an answer to the existing complaint within 20 days after plaintiff's time to serve and file an amended complaint has expired; and it is further
ORDERED that if plaintiff does serve and file an amended complaint in conformity herewith within such time, then (1) the defendants 550 Grand LLC, Eco-Build Construction, Michael T. Schlegel, and Cynthia A. Schlegel shall serve an answer to the amended complaint, (2) the defendants Schlegel LLC and/or Eco-Build Construction, as applicable, shall either serve an answer or otherwise respond to the amended complaint, in each instance, within 20 days after service of the amended complaint on their counsel, and (3) the defendant Timothy Phillips, who already has answered, shall serve an amended answer to the amended complaint within 20 days after service of the amended complaint on his counsel; and it is further
ORDERED that the branch of the Schlegel defendants' motion to dismiss plaintiff's breach of contract/third-party beneficiary claim (the tenth cause of action) against the contractor Eco-Build Construction is denied; and it is further
ORDERED that the remaining branch of the Schlegel defendants' motion to dismiss the complaint against them on the basis of documentary evidence under CPLR 3211 (a) (1) and for lack of capacity to sue under CPLR 3211 (a) (3) is denied.
In Seq. No. 3, it is hereby
ORDERED that the branch of the architect's motion to dismiss the contract and negligence claims against it (the seventh and eighth causes of action, respectively) as time-barred under CPLR 3211 (a) (5) is granted; and it is further
ORDERED that the branch of the architect's motion to dismiss the fraud, contract, and [*14]negligence claims against it (the fifth, seventh, and eighth causes of action, respectively) for failure to state a cause of action under CPLR 3211 (a) (7) is granted; and it is further
ORDERED that, based on the foregoing, the complaint against the architect is hereby dismissed in its entirety without costs or disbursements, and the action is hereby severed and continued against the remaining defendants; and it is further
ORDERED that the remaining branch of the architect's motion to dismiss the complaint against it on the basis of documentary evidence under CPLR 3211 (a) (1) is denied.
Counsel to the remaining parties are directed to appear for a preliminary conference
in Room ____ on _____ __, 2014, at 9:30 This constitutes the decision, order, and judgment of the Court.
E N T E R,
J. S. C.
Footnote 1:A "light well" is an
"[u]nroofed open shaft within the perimeter of a building that allows light to reach
internal windows" (Wiley Dictionary of Civil Engineering & Construction [Len F.
Webster ed. 1997], at 344).
Footnote 2:The complaint takes
contradictory approaches to the same factual circumstances. It alternatively alleges that
the Schlegel defendants and the architect, or either of them, were responsible for
applying for a J-51 tax abatement. Compare Complaint ¶ 15 ("According to
the Sponsor, The Architect' was delegated by the Sponsor with the responsibility of
applying for and obtaining applicable J-51 tax rebates or reductions . . ., as represented in
the Offering Plan. Upon information and belief, Ghattas and/or [Phillips] never filed the
application and recklessly let the deadline for such tax benefits close.") with
¶ 34 ("The Sponsor and the Individual Defendants repeatedly represented
throughout the Offering Plan that Sponsor had already applied for tax exemption under
section J-51 . . . and promised that Sponsor will use its best efforts to obtain the
benefits.' [T]he Sponsor or, in the alternative[,] Defendants blatantly breached this duty
and Sponsor flat-out misrepresented the facts in the Offering Plan."), with ¶
138 ("[t]he Sponsor failed to even attempt to obtain the promised tax abatement, in
violation of the agreement"), and with ¶ 180 ("the Sponsor and Individual
Defendants made false representations and omissions of material fact to the Unit Owners,
including direct misrepresentations as to the status of the J-51 abatement application").
Footnote 3:Compare
Complaint ¶ 130 (alleging, in support of the contract claim, that the sponsor
"represented that the construction of the Building and the Units . . . would be
substantially in accordance with the Offering Plan and the Plans and Specifications")
with ¶ 133 and 136 (alleging, in support of the express warranty claim, that
"[i]n the Offering Plan, as incorporated in the Purchase Agreements, the Sponsor
promised and represented that the Building . . . would be constructed in accordance with
applicable laws, governmental regulations and codes" and that "[t]he Sponsor failed to
construct the Building and Units in a manner and quality comparable to prevailing local
standards and in accordance with the relevant plans and specifications") and with
¶¶ 152, 156 (alleging, in support of the implied warranty claim, that "[a]
warranty is implied in the Purchase Agreements between the Sponsor and the Unit
Owners pursuant to which the Sponsor impliedly promised and warranted that the
Building would be designed and constructed in a skillful manner free from material
defects" and that "[b]y reason of Sponsor's breach of its implied warranty, the
Condominium and Unit Owners have sustained and will continue to sustain substantial
damages").
Footnote 4:The sponsor's remaining
arguments can be summarily disposed. The sponsor correctly notes that General Business
Law article 36-B has superseded the "Housing Merchant Implied Warranty" (see
Fumarelli v Marsam Dev., Inc., 92 NY2d 298, 300-301 [1998]). The sponsor's
disclaimer of statutory warranties (in ¶ 20 at 56 of the offering plan) is enforceable
under General Business Law § 777-b (3). Contrary to the sponsor's position,
however, an individual purchaser's time to give notice of defects under the sunset
provision began to run from the time of closing of such purchaser's unit, rather than from
the first date on which title to a unit was conveyed to a purchaser (Apr. 25, 2009).
According to Ms. Blahoski's affidavit, she notified the sponsor, by certified mail within
one year of purchase, of the defects with her unit and, thus, satisfied the notice
requirements of the sunset provision.
Footnote 5:The Martin Act, General
Business Law § 352-e applies to the offering of securities consisting of participation
interests in real estate, including condominium units. The Martin Act authorizes the
Attorney General to enforce its provisions and to implement rules and regulations
in respect of its disclosure requirements for the condominium units
(see 13 NYCRR part 20).
Footnote 6:CPLR 3016 (b) provides
that "[w]here a cause of action . . . is based upon misrepresentation [or] . . . fraud . . ., the
circumstances constituting the wrong shall be stated in detail."
Footnote 7:See Complaint
¶ 132 ("The purchase agreements executed between each Unit Owner and the
Sponsor . . . contained all relevant terms and conditions and incorporated by reference all
promises, representations, statements, reports, opinions, plans, drawings, specifications,
selling brochures, advertisements, and warranties in the Offering Plan."), ¶ 139
("The Sponsor's failures amount to a breach of its obligations under the Purchase
Agreements.").
Footnote 8:The First Department's
decision in Manas is instructive. There, the plaintiff pleaded a contract claim
alongside her claims of fraud and fraudulent inducement. In resisting a motion to
dismiss, she relied on a well-established principle that a fraud-based cause of action may
lie where the plaintiff pleads a breach of a duty that is separate from a contract. The First
Department, however, dismissed her fraud and fraudulent inducement claims as
duplicative of her contract claim, explaining (at page 454):
"Here, plaintiff does allege with respect to the cause of action for fraudulent
inducement that at the time defendants made the alleged representations regarding the
short and long-term compensation plans, defendants did not intend to compensate
plaintiff in conformity with their promises. Similarly, with respect to her cause of action
for fraud, plaintiff alleges that defendants did not intend to compensate plaintiff in
conformity with the promises and assurances concerning the short and long-term
compensation plans. However, these allegations are not sufficient. Rather, because they
are merely general allegations that defendants entered into a contract while lacking the
intent to perform it, the allegations are insufficient to support the fraud-based claims"
(internal quotation marks, alterations, and citation omitted).
Footnote 9:But see 511 W.
232nd Owners Corp. v Jennifer Realty Co., 285 AD2d 244, 248 (1st Dept 2001);
Board of Mgrs. of Crest Condominium v City View Gardens Phase II, LLC, 35
Misc 3d 1223(A), 2012 WL 1660679, *10, 2012 NY Slip Op 50826(U) (Sup Ct, Kings
County 2012).
Footnote 10:A claim under
General Business Law § 349 or § 350 is subject to a three-year statute of
limitations (see CPLR 214 [2] see also Corsello v Verizon NY, Inc., 18 NY3d 777, 789
[2012], reargument denied 19 NY3d 937 [2012]). The sponsor has not moved for
dismissal of these claims as time-barred. This is understandable, given that at least two
purchasers acquired their units within three years before the commencement of this
action (see Recording and Endorsement Cover Pages for Mary K. Lewis, unit 2S,
deed dated July 21, 2011; Georgianna Fouquet, unit 1, deed dated Aug. 16, 2011).
Footnote 11:See Purchase
Agreement, § 15 at 9-10 and § 14 at 8-9; see also Offering Plan,
§ 15 at 55.
Footnote 12:Actually, the
complaint defines the term "sponsor" twice — in the introductory paragraph to
mean Schlegel LLC and later in ¶ 9 to mean collectively 550 Grand LLC, the
developer, Schlegel, LLC, the Schlegels, and Phillips.
Footnote 13:The contractor is not
seeking dismissal of the negligence claim (the ninth cause of action) against it. Although
there is some confusion as to whether plaintiff asserts a fraud claim (the fifth cause of
action) against the contractor, a fair reading of the complaint shows that plaintiff asserts
no fraud claim against the contractor. Whereas the fraud claim is entitled as the action
against "all" defendants and presumably includes the contractor, the latter is mentioned
only once in the body of this cause of action (see Complaint ¶ 196 ["As a
direct and proximate result of the fraud, deception and misrepresentations of Individual
Defendants, Sponsor, Contractor and Ghattas. . . ."] [emphasis added]). Equally
important, the prayer for relief for the fraud claim (in clause "e") is limited to the
sponsor, the architect and the individual defendants, and does not encompass the
contractor.