| J & E Indus. of Ossining, Inc. v City of Peekskill |
| 2015 NY Slip Op 51315(U) [48 Misc 3d 1230(A)] |
| Decided on September 11, 2015 |
| Supreme Court, Westchester County |
| Giacomo, J. |
| Published by New York State Law Reporting Bureau pursuant to Judiciary Law § 431. |
| This opinion is uncorrected and will not be published in the printed Official Reports. |
J & E
Industries of Ossining, Inc., Plaintiff,
against City of Peekskill and Peekskill Housing Authority, Defendants. |
The following papers numbered 1 to 11 were read on defendant Peekskill Housing Authority's ("PHA") motion to dismiss the complaint and plaintiff's cross motion for sanctions.
PAPERS NUMBEREDIn 2007, plaintiff performed work for defendants at the Dunbar Heights housing complex. On October 1, 2007 it sent a bill to defendants in the amount of $207,000 for services provided.
On September 17, 2013, plaintiff commenced an action (Action No.1) under index no. 64274/2013 by filing a summons with notice with the Westchester County Clerk to preserve the 6-year breach of contract statute of limitations. On September 27, 2013 plaintiff filed a notice of claim with PHA. On November 6, 2013, plaintiff served PHA with the Summons with Notice.
By decision and order dated May 21, 2014, this Court granted PHA's motion to dismiss the complaint on the ground that pursuant to NY Public Housing Law § 157(1), plaintiff was required to file a notice of claim with PHA 30 days before commencing a law suit. Therefore, the Court held that plaintiff did not satisfy the condition precedent to the commencement of Action #1 with respect to PHA.
On November 21, 2014, plaintiff commenced this action (Action #2) making identical allegations to those in Action #1.
On January 26, 2015, PHA moved to dismiss Action #2 and plaintiff cross moved for the imposition of sanctions.
On May 6, 2015, the Appellate Division Second Department affirmed this Court's May 21, 2014 decision and order in J & E Industries of Ossining, Inc. v. Peekskill Housing Authority, 128 AD3d 638 [2015]).
In light of the Appellate Division's decision in Action #1, this Court requested additional submissions from the parties regarding their motions in Action #2.
PHA now moves to dismiss the complaint on the ground that the Appellate Division's affirmance of the dismissal of Action #1 is res judicata and precludes plaintiff from commencing Action #2. Further, Action #2 is time barred because the summons and complaint filed in this action was filed 6 years after the breach of contract action accrued on October 1, 2007.
Plaintiff argues that pursuant to CPLR 205(a) it is entitled to a 6-month tolling of the statute of limitations since the May 6, 2015 decision of the Appellate Division, Second Department was a final termination of the action.
CPLR 205(a) provides:
Here, plaintiff claims that since it filed a notice of claim on September 27, 2013 and then commenced Action # 2 on November 21, 2014 it satisfied the condition precedent of NY Public Housing Law § 157(1), and it is entitled to a 6 month tolling of the statute of limitations pursuant to CPLR 205(a). Plaintiff argues that it had six months after the May 6, 2015 Appellate Division decision to recommence its action. Therefore, it's commencement of Action #2, albeit prior to the Appellate Division decision, is timely.
However, in order to get the benefit of CPLR 205(a), Action #1 would have had to have been timely commenced. While the summons and complaint was filed on September 17, 2013, before the expiration of the statute of limitations, the action was not timely commenced because the condition precedent of the filing of the notice of claim pursuant to the NY Public Housing Law § 157(1) was not satisfied. Therefore, contrary to plaintiff's contentions, it does not get the benefit of CPLR 205(a). (see Yonkers Contracting Co. v. Port Authority Trans-Hudson Corp., 93 NY2d 375, 378 [1999]). Moreover, the dismissal of Action #1 was a dismissal on the merits and, thus, plaintiff is not entitled to the 6-month grace period of CPLR 205(a) (see Matter of Westchester Joint Water Works v Assessor of City of Rye, 120 AD3d 1352 [2nd Dept 2014]; cf. Goldstein v. New York State Urban Development Corp., 13 NY3d 511 [2009]).
Accordingly, PHA's motion is GRANTED solely to the extend of dismissing the complaint and the motion is DENIED in all other respects. Plaintiff's cross motion for sanctions is DENIED.
September 11, 2015
HON. WILLIAM J. GIACOMO, J.S.C.